Tunnel vision

cart-horse

 

Gozo’s connectivity issues are considered as a problem when in reality they define Gozo and determine its distinct features. Unfortunately, in this respect both the government and the opposition have developed a tunnel vision, that is they tend to focus on just one view and ignore everything else.

The latest twist in the current debate is the declaration by the Finance Minister in his budget statement earlier this month that the feasibility study commissioned by Transport Malta, together with the Gozo Business Chamber has been concluded positively  and that the next step would be  the commissioning of a technical and geological study relative to the projected tunnel across the Gozo Channel.

Transport Malta, prodded by the Gozo Business Chamber, seems to be bent on putting the cart before the horse as it is inconceivable how a feasibility study could be concluded without first having identified all the geological issues and examined them in detail.  Knowing that the Gozo Channel contains a number of geological faults, including active ones, leads to the logical preliminary conclusion that geological studies of the area proposed to be tunnelled could have a substantial bearing on the technical parameters of the project. This would include the specific  route to be selected, the actual works to be carried out and the costings. The geological studies could also lead to a technical recommendation to select an alternative solution other than boring a tunnel below the seabed .

When the PN-led government placed the issue on the national agenda, former Minister Chris Said gave his guesstimate that the tunnel would cost in the region of €150 million. We have recently been informed that this guesstimate has increased substantially to between €250 and €300 million.

These guesstimates are on the low side, because when the geological issues have been examined the estimate could well shoot up to over €1 billion- this being around 4 times what has been taken into consideration in the so-called “feasibility study”.

These type of project very rarely follow estimated costs. The tunnel linking the Marsa and Delimara powers stations in Malta, for example, overshot its projected costs by around 100% due to the absence of adequate geological information. As a result, parts of the  tunnel caved in during works, necessitating substantial additional work, including redirecting parts of it. On the other hand,  expenditure on the Channel Tunnel linking Folkestone in Kent to Coquelles near Calais exceeded the projected estimates by around 80% notwithstanding the availability of detailed geological studies.

Last week, one of the Sunday newspapers referred to a survey carried out by the Gozo Tourism Association which indicates that 64% of tourism operators in Gozo are adamantly against the proposed tunnel because the direct result of this would be to render Gozo as an appendage of Malta. Gozo would be transformed into a one- day destination, just like most of the other tourism attractions spread over the Maltese islands.

Gozitan tourism operators have a very valid point, as the direct result of this tunnel vision is that Gozo would be transformed from an island into a remote village. Most hotels in Gozo as well as the flats and farmhouses available to let, could then require the identification of another use.

This matter has not yet been examined and yet it is fundamental to the decision-making process and should have been the first step in the whole exercise.

All this muddle and I have not yet commenced discussing the environmental impacts of the proposed tunnel!

The tunnel will generate large quantities of rock which require disposal. The precise amount would depend on the route to be followed (and consequently the length of the tunnel) as well as the selected design (the cross sectional area) and could be anything between one and two million cubic metres of fragmented rock.

In addition, the proposed point of entry of the tunnel at Iċ-Ċumnija on the outskirts of Mellieħa, would most probably be accessed through a new road network in the area immediately behind the Għadira Nature Reserve and bird sanctuary. This means that all the environmental issues which were discussed when the proposed TEN-T network was being debated will once more be of relevance.

There are many other ways through which Gozo’s connectivity issues can be addressed and there are certainly more cost effective ways than the proposed tunnel. The costs to be considered are not just financial: they include social and environmental costs, which should be considered on the drawing board and not as an afterthought.

This is the problem with the tunnel vision – you just have one view, excluding all the others.

Il-mina bejn Malta u Għawdex

Gozo_tunnel_route_alignment_options

 

Ma nafx jekk il-Ministru tal-Finanzi kienx jaf x’inhu jgħid meta qal li l-feasibility study “ikkummissjonat minn Transport Malta u l-Gozo Business Chamber” dwar il-mina bejn Malta u Għawdex kien lest. Imbagħad fis-sentenza ta’ wara jgħidilna li l-pass li jmiss issa huwa l-istudju tekniku u ġeoloġiku dwar il-mina.

Il-mistoqsija toħroġ waħedha: kif tista’ tagħmel feasibility study sura, jiġifieri studju dwar jekk jaqbilx li jsir il-proġett, meta għadek ma lestejtx l-iktar studju importanti: dak ġeoloġiku.

Dan ilu żmien jingħad minn kull min jaf l-affarijiet.

Jiena ktibt dwar dan kważi ħames snin ilu.

Iktar importanti milli ktibt jien, illum tkellem mat-Times il-ġeoloġista Peter Gatt. Tkellem ukoll mat-Times nhar it-3 ta’ Frar 2011.

Dr Peter Gatt jispjega fit-Times tal-lum għaliex qabel ma jsir l-istudju ġeoloġiku ma tista’ tikkonkludi xejn. Dan l-istudju hu “a vital first step”. Dan minħabba li l-istudju ġeoloġiku, jekk isir sewwa, jidentifika l-problemi ġeoloġiċi fuq ir-rotta li tkun ser titħaffer. Min-naħa l-oħra, jispjega Dr Gatt, jekk l-istudju ma jsirx, jew ma jsirx sewwa l-ispejjes tal-proġett jimmoltiplikaw. Kif ġara, jgħidilna Dr Gatt, fil-mina bejn Delimara u l-Marsa [bejn iż-żewġ power stations] li swiet id-doppju ta’ dak ippjanat minħabba li, billi ma kienx hemm informazzjoni ġeoloġika adegwata f’idejn min fassal il-proġett, kien hemm kollass tal-blat f’diversi partijiet tal-mina.

Dr Gatt isemmi l-eżempju tal-istudju ġeoloġiku li sar bi preparazzjoni għaċ-Channel Tunnel bejn l-Ingilterra u Franza. Dan l-istudju dam 50 sena biex sar u minkejja dan, l-ispiża taċ-Channel Tunnel xorta varjat bi 80% mill-istima oriġinali.

Meta wieħed iqis dan kollu ma nafx x’feasibility study sar!

Qalulna ukoll (mhux fil-baġit) li l-mina ser tiġi tiswa madwar €250 miljun. Meta tqis l-ispejjes li jistgħu jkunu meħtieġa minħabba l-kundizzjonijiet ġeoloġiċi taħt il-Fliegu bejn Malta u Għawdex, naħseb li din l-istima hi baxxa ħafna. Fil-fatt jiena fl-artiklu tiegħi tal-2011 kont għidt li probabbilment li l-ispiża tkun bejn €1 biljun u €1.5 biljun. Dan kont ibbażajtu fuq l-ispiża stmata għall-mina bejn il-gżira Daniża ta’ Lolland u l-gżira Ġermaniża ta’ Fehmarn li kienet qed tkun diskussa f’dak iż-żmien. Għalkemm dawn huma stimi imma xorta hemm diskrepanza kbira li mhiex ġustfikata.

Hemm dawn il-problemi kollha u għandna ma bdejniex nitkellmu dwar impatti ambjentali, li minnhom hemm bosta.

Il-mina, biex issir, ser tiġġenera kwantità kbira ta’ blat imqatta. Dan ivarja skond id-diżinn u jista’ jammonta sa żewġ miljun metri kubi ta’ blat. Hemm ukoll is-siti Natura 2000 li qegħdin viċin ħafna taż-żona fejn ser tiżbokka l-mina fl-inħawi taċ-Ċumnija limiti tal-Mellieħa.

Imma l-feasibility study lest, qalilna l-Ministru!