Il-mina t’Għawdex: ħmar il-lejl

Il-Ministru Ian Borg, iktar kmieni din il-ġimgħa, infurmana li kien qed jaħdem biex iwettaq il-ħolma ta’ diversi Għawdxin billi jmexxi l-quddiem il-proċess tal-mina taħt qiegħ il-baħar bejn Malta u Għawdex. Wara dibattitu li ilu għaddej is-snin hu ċar li iktar milli jwettaq il-ħolm ikun aħjar jekk Ian Borg jipprepara ruħu għal ħmar il-lejl.

Saru studji ġejoloġiċi imma lanqas il-konklużjonijiet ġenerali dwarhom ma nafu. Għadhom mistura qieshom xi sigriet tal-istat. Tliet snin ilu l-ġejoloġista Peter Gatt kien ġibed l-attenzjoni għall-fatt li l-mina tal-Enemalta bejn il-power station tal-Marsa u Delimara kienet swiet id-doppju ta’ dak ippjanat u dan minħabba kollass tal-blat f’diversi punti matul il-mina nnifisha. Dan kien seħħ bħala riżultat tan-nuqqas ta’ informazzjoni ġejoloġika meta ġiet imfassla l-mina. Kieku dan kellu jseħħ waqt li jkun għaddej ix-xogħol fuq il-mina bejn Malta u Għawdex hu inevitabbli li jkollna problemi kbar, inkluż possibilment numru ta’ mwiet.

Hu fatt magħruf li fil-Fliegu hemm diversi kisriet ġejoloġiċi (geological faults). Tajjeb li nirrealizzaw li tnejn mill-proposti għall-mina, li saru minn Mott MacDonald, il-konsulenti ta’ Transport Malta, jgħaddu minn dawn il-kisriet.

Li jkunu eżaminati l-kampjuni tal-blat f’laboratorju, anke jekk għal ftit ġimgħat, bla dubju jżid l-għarfien tal-ġejoloġija taż-żona imma dan mhux biżżejjed biex fuqu jittieħdu deċiżjonijiet dwar id-diżinn tal-proġett. Biżżejjed nifhmu li minkejja l-istudji ġejoloġiċi dettaljati fuq numru kbir ta’ snin, ix-xogħol fuq il-mina bejn l-Ingilterra u Franza, iċ-Channel Tunnel, kellu jieqaf u jkun devjat diversi drabi minħabba li t-tħaffir iltaqa’ ma problemi ġejoloġici li ma kien hemm l-ebda indikazzjoni tagħhom fl-istudji dettaljati!

L-istudji serji jieħdu ż-żmien biex isiru: ma jistgħux ikunu mgħaġġla minħabba data determinata minn agenda politika.

Tliet snin ilu, Transport Malta, flimkien mal-Kamra tal-Kummerċ Għawdxija kkummissjonaw studju ekonomiku, ferm qabel ma biss bdew l-istudji ġejoloġiċi. L-istudju kien intitolat Establishing a Permanent Link between the Island of Gozo and Mainland Malta: An Economic Cost Benefit Analysis of Available Strategic Options, li kien sar minn E-Cubed Consultants. Dan l-istudju kien argumenta li t-traffiku bejn il-gżejjer kien ipproġettat li fuq perjodu ta’ 15il sena jiżdied minn medja ta’ 3000 moviment kuljum għal 9000 moviment kuljum. Argument li jmur kontra l-Pjan Nazzjonali għat-Trasport approvat fl-2015 ukoll.

Il-mina proposta teħtieġ ammont kritiku ta’ movimenti ta’ karozzi li jħallsu biex jgħaddu mill-mina u per konsegwenza minn fuqhom jinġabru l-ispejjes tal-mina kif ukoll il-profitti tal-operaturi. Fi ftit kliem il-mina, biex tirnexxi tiddependi minn moviment kbir ta’ karozzi kuljum. Dan imur kontra l-politika dwar it-trasport tal-lum, li ta’ l-inqas fuq il-karta, timmira għal tnaqqis ta’ karozzi mit-toroq tagħna. Din hi materja li bla dubju għandha tkun eżaminat mill-istudju fuq l-impatti ambjentali (EIA) dwar il-mina proposta. Dan l-istudju għadu fl-istadji inizzjali tiegħu u dan wara li l-Awtorità dwar l-Ambjent u r-Riżorsi ftit ġimgħat ilu approvat dak li għandu jkun indirizzat (terms of reference) minn dan l-istudju. L-EIA hu stadju essenzjali li minnu jeħtieġ li jgħaddi l-proġett.

Għaldaqstant, kien irresponsabbli l-Ministru tat-Trasport, meta, iktar kmieni din il-ġimgħa, ħabbar li fi żmien sitt xhur kienet ħierġa sejħa internazzjonali għall-offerti għall-mina bejn Malta u Għawdex. Dan ifisser li dawn l-istudji huma irrelevanti? Fl-opinjoni tiegħi il-Ministru  qiegħed jagħti  dan il-messaġġ ċar u tond.

Din hi l-agħar forma ta’ governanza ħażina għax jimmina l-isforzi tal-awtoritajiet fil-qadi ta’ dmirijiethom. B’dan il-ħsieb jiena ktibt lill-Ombudsman u tlabtu jinvestiga dan in-nuqqas ta’ governanza tajba. Il-Gvern għandu jkollu l-paċenzja li jistenna sakemm ikunu konklużi l-istudji ambjentali qabel ma jieħu d-deċiżjonijiet.

 

Ippubblikat fuq Illum : Il-Ħadd 16 ta’ Diċembru 2018

Gozo tunnel nightmares

Minister Ian Borg informed us, earlier this week, that he seeks to turn into reality a Gozitan “long-held dream” by starting the process for a Malta-Gozo tunnel below the seabed. After debating the matter for years, it is clear that rather more than dreams, Ian Borg should prepare himself for a nightmare.

Geological studies have now been carried out and the results therof are being treated as some state secret. Three years ago, geologist Peter Gatt had drawn attention to the fact that the Enemalta tunnel between the Marsa power station and Delimara had a cost overrun of 100 per cent as a result of rock collapse along several points of the tunnel. This had occurred due to inadequate geological information fed into the design process. If the same were to happen during the Malta-Gozo tunnel works, a series of disasters, including possibly loss of life, would be inevitable.

It is a known fact that the Gozo channel is full of geological faults. It is pertinent to note that two of the tunnel options put forward by Transport Malta advisors Mott MacDonald pass through an active fault in the Gozo channel.

Taking borehole samples and examining them in a laboratory over a few weeks certainly increases our knowledge of the geology of the area but it is nowhere near the sufficient knowledge on the basis of which one can conclude the design parameters of the project. Suffice it to point out that notwithstanding the detailed geological studies spanning over many years and underpinning planning for the Channel Tunnel linking Folkestone in Kent and Coquelles near Calais, the drilling of the tunnel had to be deviated at certain points because of unpredicted geological formations.

Serious studies take years to conclude: they cannot be rushed to meet a deadline set by a political agenda.

Feasibility studies have been carried out some time ago, long before the geological studies were even taken in hand. Three years ago, the Gozo Business Chamber in conjunction with Transport Malta commissioned a study entitled Establishing a Permanent Link between the Island of Gozo and Mainland Malta: An Economic Cost Benefit Analysis of Available Strategic Options. In the study, which was carried out by E-Cubed Consultants, it was argued that the average annual daily traffic (AADT) between the islands is projected to increase from 3000 to 9000 vehicle movements over a 15-year period.

This feasibility study makes assumptions which run counter to the National Transport Master Plan objective of reducing cars from our roads.

Basically, the proposed tunnel requires a critical mass of vehicular movements which would be subject to the payment of a toll and hence contribute to the recovery of the capital outlay, maintenance costs and profits. This runs counter to current Maltese Transport policy, which (at least on paper) aims to reduce the use of private cars from our roads.

This is an issue which would undoubtedly be examined by the Environmental Impact Assessment (EIA) on the proposed Tunnel which study is currently in its initial stages after the Environment and Resources Authority recently approved the terms of reference of such a study. The EIA is an essential stage of the assessment of the project.

It was therefore irresponsible for the Minister of Transport, earlier this week, to announce that within six months an international call for tenders would be issued relative to the Malta-Gozo undersea Tunnel. Does this mean that the government considers the EIA irrelevant? This, in my opinion is the clear message being conveyed.

It is the worst form of bad governance as it undermines the efforts of the established authorities in carrying out their responsibilities. With this in mind, I have written to the Ombudsman and asked him to investigate this breach of good governance. Government should have the patience of awaiting the outcome of the EIA before taking any further decisions.

published in The Malta Independent on Sunday : 16 December 2018

Tunnel vision

cart-horse

 

Gozo’s connectivity issues are considered as a problem when in reality they define Gozo and determine its distinct features. Unfortunately, in this respect both the government and the opposition have developed a tunnel vision, that is they tend to focus on just one view and ignore everything else.

The latest twist in the current debate is the declaration by the Finance Minister in his budget statement earlier this month that the feasibility study commissioned by Transport Malta, together with the Gozo Business Chamber has been concluded positively  and that the next step would be  the commissioning of a technical and geological study relative to the projected tunnel across the Gozo Channel.

Transport Malta, prodded by the Gozo Business Chamber, seems to be bent on putting the cart before the horse as it is inconceivable how a feasibility study could be concluded without first having identified all the geological issues and examined them in detail.  Knowing that the Gozo Channel contains a number of geological faults, including active ones, leads to the logical preliminary conclusion that geological studies of the area proposed to be tunnelled could have a substantial bearing on the technical parameters of the project. This would include the specific  route to be selected, the actual works to be carried out and the costings. The geological studies could also lead to a technical recommendation to select an alternative solution other than boring a tunnel below the seabed .

When the PN-led government placed the issue on the national agenda, former Minister Chris Said gave his guesstimate that the tunnel would cost in the region of €150 million. We have recently been informed that this guesstimate has increased substantially to between €250 and €300 million.

These guesstimates are on the low side, because when the geological issues have been examined the estimate could well shoot up to over €1 billion- this being around 4 times what has been taken into consideration in the so-called “feasibility study”.

These type of project very rarely follow estimated costs. The tunnel linking the Marsa and Delimara powers stations in Malta, for example, overshot its projected costs by around 100% due to the absence of adequate geological information. As a result, parts of the  tunnel caved in during works, necessitating substantial additional work, including redirecting parts of it. On the other hand,  expenditure on the Channel Tunnel linking Folkestone in Kent to Coquelles near Calais exceeded the projected estimates by around 80% notwithstanding the availability of detailed geological studies.

Last week, one of the Sunday newspapers referred to a survey carried out by the Gozo Tourism Association which indicates that 64% of tourism operators in Gozo are adamantly against the proposed tunnel because the direct result of this would be to render Gozo as an appendage of Malta. Gozo would be transformed into a one- day destination, just like most of the other tourism attractions spread over the Maltese islands.

Gozitan tourism operators have a very valid point, as the direct result of this tunnel vision is that Gozo would be transformed from an island into a remote village. Most hotels in Gozo as well as the flats and farmhouses available to let, could then require the identification of another use.

This matter has not yet been examined and yet it is fundamental to the decision-making process and should have been the first step in the whole exercise.

All this muddle and I have not yet commenced discussing the environmental impacts of the proposed tunnel!

The tunnel will generate large quantities of rock which require disposal. The precise amount would depend on the route to be followed (and consequently the length of the tunnel) as well as the selected design (the cross sectional area) and could be anything between one and two million cubic metres of fragmented rock.

In addition, the proposed point of entry of the tunnel at Iċ-Ċumnija on the outskirts of Mellieħa, would most probably be accessed through a new road network in the area immediately behind the Għadira Nature Reserve and bird sanctuary. This means that all the environmental issues which were discussed when the proposed TEN-T network was being debated will once more be of relevance.

There are many other ways through which Gozo’s connectivity issues can be addressed and there are certainly more cost effective ways than the proposed tunnel. The costs to be considered are not just financial: they include social and environmental costs, which should be considered on the drawing board and not as an afterthought.

This is the problem with the tunnel vision – you just have one view, excluding all the others.

Il-mina bejn Malta u Għawdex

Gozo_tunnel_route_alignment_options

 

Ma nafx jekk il-Ministru tal-Finanzi kienx jaf x’inhu jgħid meta qal li l-feasibility study “ikkummissjonat minn Transport Malta u l-Gozo Business Chamber” dwar il-mina bejn Malta u Għawdex kien lest. Imbagħad fis-sentenza ta’ wara jgħidilna li l-pass li jmiss issa huwa l-istudju tekniku u ġeoloġiku dwar il-mina.

Il-mistoqsija toħroġ waħedha: kif tista’ tagħmel feasibility study sura, jiġifieri studju dwar jekk jaqbilx li jsir il-proġett, meta għadek ma lestejtx l-iktar studju importanti: dak ġeoloġiku.

Dan ilu żmien jingħad minn kull min jaf l-affarijiet.

Jiena ktibt dwar dan kważi ħames snin ilu.

Iktar importanti milli ktibt jien, illum tkellem mat-Times il-ġeoloġista Peter Gatt. Tkellem ukoll mat-Times nhar it-3 ta’ Frar 2011.

Dr Peter Gatt jispjega fit-Times tal-lum għaliex qabel ma jsir l-istudju ġeoloġiku ma tista’ tikkonkludi xejn. Dan l-istudju hu “a vital first step”. Dan minħabba li l-istudju ġeoloġiku, jekk isir sewwa, jidentifika l-problemi ġeoloġiċi fuq ir-rotta li tkun ser titħaffer. Min-naħa l-oħra, jispjega Dr Gatt, jekk l-istudju ma jsirx, jew ma jsirx sewwa l-ispejjes tal-proġett jimmoltiplikaw. Kif ġara, jgħidilna Dr Gatt, fil-mina bejn Delimara u l-Marsa [bejn iż-żewġ power stations] li swiet id-doppju ta’ dak ippjanat minħabba li, billi ma kienx hemm informazzjoni ġeoloġika adegwata f’idejn min fassal il-proġett, kien hemm kollass tal-blat f’diversi partijiet tal-mina.

Dr Gatt isemmi l-eżempju tal-istudju ġeoloġiku li sar bi preparazzjoni għaċ-Channel Tunnel bejn l-Ingilterra u Franza. Dan l-istudju dam 50 sena biex sar u minkejja dan, l-ispiża taċ-Channel Tunnel xorta varjat bi 80% mill-istima oriġinali.

Meta wieħed iqis dan kollu ma nafx x’feasibility study sar!

Qalulna ukoll (mhux fil-baġit) li l-mina ser tiġi tiswa madwar €250 miljun. Meta tqis l-ispejjes li jistgħu jkunu meħtieġa minħabba l-kundizzjonijiet ġeoloġiċi taħt il-Fliegu bejn Malta u Għawdex, naħseb li din l-istima hi baxxa ħafna. Fil-fatt jiena fl-artiklu tiegħi tal-2011 kont għidt li probabbilment li l-ispiża tkun bejn €1 biljun u €1.5 biljun. Dan kont ibbażajtu fuq l-ispiża stmata għall-mina bejn il-gżira Daniża ta’ Lolland u l-gżira Ġermaniża ta’ Fehmarn li kienet qed tkun diskussa f’dak iż-żmien. Għalkemm dawn huma stimi imma xorta hemm diskrepanza kbira li mhiex ġustfikata.

Hemm dawn il-problemi kollha u għandna ma bdejniex nitkellmu dwar impatti ambjentali, li minnhom hemm bosta.

Il-mina, biex issir, ser tiġġenera kwantità kbira ta’ blat imqatta. Dan ivarja skond id-diżinn u jista’ jammonta sa żewġ miljun metri kubi ta’ blat. Hemm ukoll is-siti Natura 2000 li qegħdin viċin ħafna taż-żona fejn ser tiżbokka l-mina fl-inħawi taċ-Ċumnija limiti tal-Mellieħa.

Imma l-feasibility study lest, qalilna l-Ministru!