Making hay …….. in St George’s Bay

The 23-storey Pender Gardens high-rise is nearly completed, after nearly 10 years of continuous construction activity. The application for the 31-storey Mercury House was approved last month and next Thursday, the Planning Authority Board will consider planning application PA2478/16 submitted by Garnet Investments Limited in respect of a substantial stretch of land along St George’s Bay on the outskirts of Paceville St Julian’s.

The applicant has requested the following: “Demolition of all existing buildings forming part of St. George’s Bay Hotel and ancillary facilities, Dolphin House, Moynihan House and Cresta Quay. Construction of Parking facilities, Hotels and ancillary facilities, Commercial Area, Multi Ownership holiday accommodation, Bungalows, Language school with accommodation. Restoration of the Villa Rosa and upgrading of the facilities including parking facility, kitchen and toilets all below existing site levels within the Villa Rosa Area to address catering facilities/wedding hall.”

The project includes mixed-uses covering a total site area of 48,723 square metres, a building footprint of 18,345 square metres and a total gross floor area of 82,917 square meters.

It is a small part of the area that was tentatively tackled by a draft Masterplan for Paceville which, after being rejected by public opinion was sent back to the drawing board. I consider it highly unethical for the Planning Authority to proceed with considering this application after the clear and resounding verdict of public opinion. As a minimum, the consideration of this application should have been postponed until a new, reasonable and acceptable Masterplan has received the go-ahead. A minimum effort at achieving consensus as to what development is acceptable is essential.

The Planning Authority is unfortunately insensitive to public opinion. It is amply clear that it, and those who appoint most of its Board members, are on the same wavelength as the development lobby, which is hell-bent on making hay while the sun shines. At this point in time, it is the turn of the St George’s Bay area.

The project is obviously recommended for approval in the 43-page report from the Planning Directorate.

The basic point of contention with such large-scale projects is that they are considered in isolation. Most of them would never get off the drawing board (real or virtual) if the consolidated impact of all neighbouring projects (existing or in the pipeline) are taken into account. Earlier this week, I had the opportunity to address similar concerns to the EIA public consultation on the db Group ITS site project.

Five large-scale projects are earmarked for St George’s Bay. Each will generate considerable havoc from excavation throughout construction and right through operation in the whole St George’s Bay area. Cumulatively it will be hell. Who cares?

Way back in 2006, when the Strategic Environmental Assessment Directive of the EU was about to be implemented in Malta, the Lawrence Gonzi – George Pullicino tandem rushed through the approval of the Local Plans in such a manner as to ensure that the accumulated environmental impact resulting from their implementation was not scrutinised and acted upon. The present state of affairs is the direct result of that irresponsible Gonzi-Pullicino action 12 years ago.

The Environment and Resources Authority (ERA) occasionally tries to patch things up. For example, within the framework of the ITS EIA exercise ERA suggested that the traffic assessment of the ITS and the Villa Rosa projects be consolidated. This has, however, been avoided: a case of too little, too late.

So where do we go from here?

The development lobby is maximising its efforts to make hay while the sun shines. In reality, a consolidated mess is taking shape with massively built-up areas in a relatively restricted space punctured by high rises mimicking phallic symbols of all shapes and sizes spread all over the place. Pender Place has 23 floors. Mercury House will have 31. The ITS phallus will have a 37-floor residential tower. The Villa Rosa/Cresta Quay project will have more modest heights.

Next Thursday, the Planning Authority has the opportunity to scrutinise the proposal for this Villa Rosa-Cresta Quay project. We will see once more the extent to which the concrete lobby still holds the Authority by its balls – obviously where this is applicable.

 

published in The Malta Independent on Sunday – 18 February 2018

Advertisements

Marsa: a planning mess

turkish-cemetry-marsa-malta2

The Chamber of Architects has taken the Planning Authority to task on the piecemeal local plan reviews that it has been churning out, one at a time. The latest tirade was with reference to a partial review of The Grand Harbour Local Plan (originally published in 2002) specifically with respect to a Marsa Park Site.

We have just concluded a public discussion on a Masterplan for Paceville, which was shredded by public opinion and sent back to the drawing board.

Earlier, we had the Planning Authority itself contesting whether Local Councils, NGOs and the Environment and Resources Authority  had a right to contest the decision to permit high-rises in Townsquare Sliema and in Imrieħel.

To make matters worse, instead of consolidating the environmental regulatory functions of the state, this government has opted to deliberately fragment them, thereby ensuring their reduced effectiveness by design.  In a small country such as Malta, it pays to have one consolidated authority  directed by environment professionals through whom land use planning responsibilities should be accountable.

Land use planning needs to be more focused but holistic in nature. The Chamber of Architects aptly makes the point that focusing the efforts of the partial review of the Grand Harbour Local Plan specifically on “a Marsa Business Park” without considering this within the context  of a much needed regeneration of Marsa would be a futile exercise. The decay of Marsa as an urban centre needs to be addressed at the earliest opportunity and this will not be done through piecemeal local plan reviews but through comprehensive planning “which ought to include community needs, road transport re-alignment, environment improvement and flooding mitigation measures”.

These are the basic issues which should be addressed by a local plan review concerning Marsa. Tackling major infrastructural and social problems facing the Marsa community should take precedence over any proposal for the redevelopment of the Marsa Park site. It is the whole of Marsa that should be addressed and not just one tiny corner.

The partial local plan review is ignoring the local community, just like its cousin the Paceville Masterplan did some months ago. Many years ago we learned that “planning is for people”. This seems to be no longer the case as, according to the Planning Authority, planning is apparently for business hubs, high-rises and, obviously, for developers. They seem to be very well connected, thereby ensuring that they occupy the first items of this government’s land use planning agenda.

Marsa has been forgotten over the years. With the closure of the Marsa power station now is the appropriate time to consider the various accumulated impacts on the Marsa community in order that an integrated approach to addressing them is identified. Planning is for people. That means that the Marsa community should be actively involved when these plans are being formulated, including at the drawing board stage. Land use planners should stimulate the Marsa community to speak up and involve itself in drawing up a blue print for its future.

The regeneration of Marsa is an urgent matter which should not be left unattended.

published in The Malta Independent on Sunday : 15 January 2017

Paceville: protecting the underdogs

paceville-mp-land-use

As the short time allotted for public consultation on the proposed first draft of the Paceville Masterplan approaches its conclusion, it is time for some commonsense to prevail at the Planning Authority.

On TV, last Thursday, we heard the Authority’s Executive Chairman Johann Buttigieg plotting the first steps of a U-turn on a number of contentious issues contained in the draft. This U-turn is welcome, as it is clearly being planned on the basis of the reactions of the public and the environmental NGOs to the proposed Paceville Masterplan.

The most serious point at issue is the extent to which the nine projects around which the Masterplan is woven will engulf properties belonging to residents and small scale business people. It will hopefully now be clear, once and for all, that no one will be coerced through threats of compulsory purchase (veiled or otherwise) to make way for any one of the nine projects.

Mr Buttigieg declared that “no-one would be forced to sell”. While this declaration is welcome, it is certainly not sufficient. Everyone is aware that there are many ways through which pressure may be brought to bear on residents and business people. It is certainly time for all stakeholders to be vigilant and present a common front.  Being constantly on the look-out may help  identify those triggering incidents such as that of the car which was recently set ablaze in St George’s Park at Paceville at the same time as residents were meeting elsewhere to discuss their reactions to the proposed Paceville Masterplan.

The Planning Authority should be proactive. It should be at the forefront when it comes to taking initiatives that make sense. A case in point is the need to implement the public domain legislation recently enacted by Parliament  in order to better protect both the coastline and the foreshore to a minimum distance of fifteen metres from the shoreline.

It is well known that there is just one stretch of coastline within the draft Paceville Masterplan boundaries that is not intensively developed: the Cresta Quay site, also referred to as the Villa Rosa site 3. This site is crying out for protection and it can be protected, yet the draft masterplan – ignoring public domain legislation  – earmarks this site for a number of high rise blocks.

This proposal, in addition to reducing the recently approved public domain legislation to hot air, runs counter to the draft masterplan philosophy of siting high-rise developments away from the coast. It seems that someone may have been pressured into having second thoughts when the Masterplan was being drafted. There is no other reasonable explanation for this contradiction.

The public consultation has revealed that the drafting of the Paceville Masterplan was flawed, as it ignored issues of fundamental importance.  However, there is till time for the Planning Authority to align the Masterplan to the expectations of stakeholders. The belated declaration by Johann Buttigieg that (after all) he too has reservations on some aspects of the Masterplan is a step in the right direction. Hopefully, this will be reflected in an overhaul of the draft and in the production of a new one which respects the stakeholders who have invested in Paceville over the years.

The investors promoting the nine projects which the Planning Authority identified may contribute to the regeneration of Paceville only if they tread carefully in full respect of residents and small-scale business people who have shaped the present-day Paceville, warts and all.

So far, this has not happened, as some of the developers think that they have some God-given right to ride roughshod over one and all. Unfortunately, the Planning Authority has generally obliged, as it has rarely been on the side of the those bearing the brunt of the bulldozer culture that has to date reigned supreme in land-use planning issues.

We await the second draft of the Paceville Masterplan, in the hope that the Planning Authority will turn a new page and assume its rightful place in protecting the underdogs.     

published in The Malta Independent on Sunday: 20 November 2016

Id-9 proġetti għal Paceville

paceville-4

Il-Master Plan ta’ Paceville hemm bżonn isir mill-ġdid. Dan hu meħtieġ għax min fassal il-pjan ma tax każ ta’ ħafna affarijiet. Reviżjoni ma hi ser issolvi xejn. Jeħtieġ li jinbidel kompletament.

L-ikbar fundamentali żball li sar, fil-fehma tiegħi, hu li l-pjan għal Paceville hu bbażat fuq id-9 proġetti kbar li hemm pendenti. Dan il-fatt fih innifsu jagħti messaġġ li l-pjan għal Paceville qiegħed hemm biex jaqdi lill-iżviluppaturi li hemm wara dawn il-proġetti. Jista’ jingħad li ma hemm xejn mistur dwar dan kollu u li l-ħsieb kien li l-iżvilupp ma jsirx bil-biċċiet imma li jkun wieħed li jħares lejn l-istampa kollha.

Imma biex jaqdu lil dawn id-9 żvilupaturi dawk li fasslu l-pjan ma tawx kaz tal-fatt li hemm mijiet ta’ persuni li tul is-snin investew ħinhom u ġidhom f’Paceville. Min f’daru u min fin-negozju tiegħu. Huma dawn in-nies li bnew Paceville li hemm illum: bil-preġji u d-difetti kollha tiegħu.

Il-pjan ta’ Paceville jeħtieġ li nanillazzawh fuq dan u mhux fuq ħsibijiet immaġinarji.

Kif jiġri dejjem, min jifhem biss biċċa żgħira minn dak li jkun qed jiġri jfittex li jiddrammatizza l-affarijiet. Dan iservi biss biex isaħħan l-irjus u ma jagħti l-ebda kontribut għal diskussjoni serja.

 

 

 

 

Konsultazzjoni ħierġa minn widnejna?

cpd-external-emergency-plan

 

Bħalissa qed jikkonsultawna spiss. Jekk jagħtux kaz ta’ dak li ngħidu, imma, dik ħaġa oħra.

Kultant naħseb ukoll li ma jagħmilx ġid li numru ta’ affarijiet importanti issir id-diskussjoni pubblika dwarhom fl-istess ħin.

Bħalissa d-diskussjoni pubblika hi iffukata fuq ta’ l-inqas tlett affarijiet importanti: fuq il-budget, fuq il-Masterplan ta’ Paceville u fuq l-impjant tal-gass fil-power station ta’ Delimara.

Iż-żmien għal dawn il-konsultazzjoniet pubbliċi hu limitat.

Il-konsultazzjoni pubblika dwar Paceville hi ikkumplikata minħabba it-tip ta’ proposti li ġew ippreżentati. Ir-rapport trid taqrah numru ta’ drabi biex tibda tifhmu mhux biss għax ikkumplikat minnu innifsu imma ukoll għax min kitbu qagħad jilgħab bil-kliem. Bil-konsegwenza li hemm numru ta’ proposti kważi moħbijin.

Min-naħa l-oħra l-konsultazzjoni pubblika dwar l-impjant tal-gass tirrikjedi eżami ta’ dokumentazzjoni voluminuza imqassma f’madwar 300 file elettroniku. Il-konsultazzjoni pubblika ser iddum 4 ġimgħat: iktar kien jagħmel sens kieku kella iddum 4 xhur minħabba li biex issir sewwa tirrikjedi ħafna xogħol.

Meta wieħed iqis li ħafna drabi jkunu l-istess nies li jinvolvu ruħhom f’din il-konsultazzjoni pubblika malajr nifhmu id-diffikultajiet li jkollna għax il-ħin hu limitat għal kulħadd.

Il-kosta tagħna lkoll?

paceville-mp-land-use

Il-Masterplan għal Paceville huwa mifrux fuq medda kbira ta’ art. Għax Paceville tmiss ma’ Pembroke, mas-Swieqi u anke ma’ San Ġiljan. Imma għandha ukoll biċċa kosta twila ġmielha, li skond minn fejn tibda tkejjilha tista’ ġġebbed bejn tlieta u erbgħa kilometri.

Il-pjan jgħidilna li ser ikun possibli li tippassiġġa mal-kosta kollha.  Imma r-realtà hi li kosta kollha ta’ Paceville hi mimlija konċessjonijiet  li l-Gvern tul is-snin ta lill-privat għan-negozju, prinċipalment negozju konness mal-baħar jew mal-lukandi.

Waqt il-laqgħa ta’ nhar l-Erbgħa tal-Kumitat Parlamentari tal-Ambjent u l-Ippjanar, id-Dipartiment tal-Propjetà tal-Gvern ippreżenta pjanta li turi il-propjeta kollha li għandu l-Gvern f’Paceville, biċċa waħda tmiss ma l-oħra. F’xi każi l-pjanta turi bejn 4 metri u 5 metri mill-kosta l-ġewwa li huma riżervati għall-aċċess tal-pubbliku, għalkemm ħafna drabi m’huwiex ċar kif dawn il-passaġġi riżervati għalina lkoll tista’ tasal għalihom.

F’Mejju li għadda b’vot unanimu l-Parlament approva emendi għall Kodiċi Civili li permezz tagħhom ġie ċċarat li l-kosta hi propjetà pubblika. Jiġifieri din hi tagħna lkoll. Mill-inqas sa 15-il metru l-ġewwa minn fejn iħabbat il-baħar. Imma fejn il-mewġ jibqa’ dieħel iktar il-ġewwa, il-15-il metru jiżdiedu ukoll, skond is-saħħa tal-baħar.

Is-serjetà kienet titlob li billi l-ewwel abbozz tal-Master Plan ta’ Paceville ġie ippubblikat għall-konsultazzjoni pubblika bosta ġimgħat wara li l-Parlament esprima ruħu b’mod tant ċar, dan kellu jagħti kaz b’serjeta kbira ta’ dak li ddeċieda l-Parlament.

Id-deċiżjoni tal-Parlament dwar il-kosta u l-art ta’ mal-plajja tfisser ħafna iktar minn sempliċi passaġġ fejn jgħaddu n-nies. Imma sfortunatament, il-konsulenti li fasslu l-Master Plan ma fehmu xejn minn dan u minflok ma fittxew kif ser jgħaddu lura lin-nies it-tgawdija ta’ partijiet ikbar mill-kosta qed jipproponulna li jkompli r-renju tal-konkos u l-azzar bi blokki għoljin tletin sular li jistgħu jinbnew viċin tal-kosta.

Issa jew hemm min ma jafx x’inhu jagħmel inkella qed jippruvaw jgħaddu lil kulħadd biż-żmien. Għax jekk il-Parlament qed jaqbel magħna u qiegħed jgħidilna li l-kosta hi tagħna lkoll, kif jiġu dawn il-konsulenti tal-Awtorità tal-Ippjanar jgħidulna li din ser jibqgħu jgawdu minnha l-ftit, biex fiha tibqa’ issir l-adorazzjoni tat-torrijiet?

pubblikat f’Illum : 16 t’Ottubru 2016

Claiming back our coast

portomaso-st-julian-s

 

The  Paceville Master Plan is rightfully subtitled : Malta’s prime coastal location.  However, it considers the coast as a money-spinner and completely ignores Parliament’s decision earlier this year to codify the importance of the coastal area through its inclusion in legislation regulating the public domain.

The Paceville Master Plan issued for public consultation on 26 September was the first opportunity for the Planning Authority, on behalf of the government – which instructs it on policy initiatives – to flesh out the bones of the declarations made in the public domain legislation, approved by Parliament in May. That it did not do so casts considerable doubt as to whether the unanimous approval by Parliament of the public domain legislation is another political gimmick.

The Paceville Master Plan covers a large tract of land bordering Pembroke to the north, Swieqi to the west, St Julian’s to the South and coastal waters to the east.  The Paceville coastline is extensive: it adds up to anything between three and four kilometres, depending on the manner of measurement.

We have been told that the Paceville coastline will be accessible through a passageway that will be created along the coast. As a matter of fact, most of the Paceville coastline is already dotted with commercial development on land which is either public property or else is subject to servitudes in favour of the state. During last Wednesday’s sitting of Parliament’s Environment and Development Planning Committee, representatives of the Government Property Department presented a drawing indicating all this property along the Paceville coastline. In a number of instances, the drawing submitted indicated passageways of a width varying between four and five metres along the coast which are obviously intended for public access, even though it is not always clear how one would be able to find their points of entry and exit.

Parliament’s approval of amendments to the Civil Code approved in May lays robust legal foundations for the protection of the coast. The government has been entrusted with protect the coast on behalf of future generations, hence it belongs to all of us, in trust, on behalf of those future generations.  The coastal perimeter extends to a minimum of 15 metres from the shoreline. To this, the newly-approved legislation adds the foreshore, which extends as far as the reach of the largest wave – a reach that can be substantial in those parts of the coastline that are exposed to the open sea.

Large sections of the Paceville coastline are developed, but there are still small pockets which are either not developed or else contain development that is not intensive. A proactive Master Plan would have identified this as an opportunity for plotting the way forward in implementing a programme for the protection of the Paceville coast.  Unfortunately, it seems that the consultants to the Planning Authority were not briefed on the matter and as a consequence there is a real danger that this opportunity will be lost.

After the current public consultation is concluded, the Planning Authority will have to examine the comments made and consider the extent to which such comments can and should be taken into consideration in the second draft of the Master Plan.

The Authority should take on board the public domain legislation in respect of the coast and plan for its implementation when it revises the first draft of Paceville Master Plan.  In the short term, this should be done in relation to those areas which are still undeveloped or underdeveloped. I would also expect the Planning Authority to plan for the longer timeframe in respect of those sections of the coastline which are already intensively developed.

This leaves one other basic issue: land reclamation. I feel that, on a policy level, Labour’s land reclamation policy is the marine equivalent of the Nationalist’s widely criticised 2006 rationalisation exercise through which the boundaries of development were irresponsibly extended.  Labour will be extending the limits to development outwards towards the sea whilst the Nationalist-led government extended the said limits towards the countryside.

The proposed Master Plan for Paceville recommends land reclamation off the Dragonara/Portomaso coastline. This is an ill-thought proposal as the area identified for land reclamation will be an extension of possibly the most intensively developed part of the Paceville coast. This proposal should undoubtedly be revisited as commonsense suggests that rather than increasing development in the area, this should, in the long term, be curtailed.

The proposed Paceville Master Plan should be utilised as a planning tool for adequate coastal management. It can, at this point in time, also be the optimum vehicle for translating the public domain legislation into practical policies through which we can start the process of reclaiming the coast for future generations.

This is an opportunity which should not be missed.

published in The Malta Independent : 16 October 2016

Il-Master Plan ta’ Paceville u l-aċċess għall-kosta

new parliament building Malta2

Fil-Parlament il-bieraħ attendejt għal laqgħa ta’ diskussjoni dwar il-Master Plan għal Paceville.

F’din il-laqgħa l-Kumitat Parlamentari għall-Ambjent u l-Ippjanar kompla d-diskussjoni mibdija f’seduta oħra. Rappresentanti tat-Taqsima tal-Propjeta’ tal-Gvern wieġbu xi mistoqsijiet li kienu għadhom pendenti kif ukoll ippreżentaw xi informazzjoni li kienet mitluba mill-Kumitat dwar art tal-Gvern f’Paceville.

F’intervent li jiena għamilt ġbidt l-attenzjoni tal-Kumitat Parlamentari għall-Ambjent u l-Ippjanar li ftit xhur ilu, l-Parlament kien approva emendi għall-Kodiċi Ċivili li permezz tagħhom ikkjarifika l-ħtieġa tal-ħarisen tal-kosta. Ma jagħmilx sens, żidt ngħid, li wara li l-Parlament approva dawn l-emendi għall-Kodiċi Ċivili b’vot unanimu issa jiġi dan l-abbozz ta’ Master Plan li prattikament jinjora dawn l-emendi.

Din hi materja kruċjali għax għandu jkun assigurat li l-aċċess għall-kosta jkun wieħed reali għal kulħadd.

Ara ukoll

Malta Today: Paceville masterplan ‘makes mockery’ of new coastal protection law, AD warns.

The Malta Independent: The Paceville Master Plan must be sent back to the drawing board.

F’Paceville, il-Gvern jaħdmek

paceville-87

 

L-Awtorità tal-Ippjanar ippubblikat, għal skop ta’ konsultazzjoni pubblika, dokument dwar Paceville. Dan hu dokument li għal darba jaħseb fit-tul. Iħares lejn l-iżvilupp ippjanat għall-inħawi fit-tul u b’mod ħolistiku. Sa hawn, tajjeb, għax hekk għandhom isiru l-affarijiet.

Imma meta tibda taqra id-dettalji, jibdew il-mistoqsijiet. L-ikbar mistoqsija hi dwar jekk l-awtoritajiet humiex, għal darb’oħra, qed jippruvaw jaħdmuna billi jinqdew bl-ippjanar għall-użu tal-art biex iħaxxnu l-bwiet ta’ uħud: dawk li jmaxtru dejjem u f’kull żmien.

Il-pjan, fost oħrajn, jidentifika l-ħtiġijiet infrastrutturali ta’ numru ta’ proġetti (disa’ fil-għadd), ewlenin fosthom toroq u probabbilment mina taħt l-art u dan biex ikun iffaċilitat l-aċċess għal Paceville li qed titfassal. Dawn il-ħtiġijiet infrastrutturali, jgħid il-masterplan għal Paceville, huma meħtieġa biex jilqgħu għall-moviment sostanzjali ta’ persuni li huwa antiċipat li dan l-iżvilupp kollu ser jiġġenera.

Min ser idaħħal idu fil-but u jagħmel tajjeb għal dawn l-ispejjes kollha?

Qed tissemma ċ-ċifra ta’ nofs biljun ewro li fil-fehma ta’ ħafna għandha tinħareġ kollha, jew tal-inqas il-parti l-kbira minnha, mill-iżviluppaturi. Għax inkella ser nerġgħu nispiċċaw fis-sitwazzjoni li huma jimpalaw il-profitti, u ħaddieħor mit-taxxi jħallas il-kontijiet. Kontijiet li ġieli inħallsuhom b’saħħitna u drabi oħra billi t-taxxi tagħna jagħmlu tajjeb għall-ħtiġijiet tagħhom.

Il-President tal-Assoċjazzjoni tal-Iżviluppaturi Sandro Chetcuti diġà qal, li, fil-fehma tiegħu, jkun aħjar jekk l-ewwel issir l-infrastruttura u wara jsir l-iżvilupp propost. Dan ifisser ħaġa waħda: li l-iżviluppaturi jippretendu li l-investiment massiċċ meħtieġ fl-infrastruttura għandu jsir mill-Gvern, mit-taxxi li jiġbor. Għax taf inti, issa għandna Gvern pro-business u għalihom dan ifisser li l-Gvern qiegħed prinċipalment għas-servizz tagħhom!

Hemm punt ieħor ta’ importanza fundamentali. Il-pjan għal Paceville jitkellem fuq ħafna ħwejjeġ. Imma jħalli barra lir-residenti li joqgħodu hemm illum. Dawk huma l-istess nies li ilhom jaqilgħu ġo fihom snin twal. Il-masterplan ma jsemmihom imkien. Jinjorhom kompletament kif diġà ġara matul is-snin. Dan iwassal għall-konklużjoni inkwetanti li r-residenti li hemm illum m’humiex meqjusa li huma importanti għal min fassal il-pjan. Ovvja għaliex: għax il-pjan hu pro-business u jpoġġi lin-nies fil-ġemb. Għax lir-residenti jqishom xkiel billi dawn dejjem joġġezzjonaw, daqqa fuq  ħaġa u daqqa fuq oħra!

Dan it-tip ta’ ippjanar ma jagħmilx ġid u m’għandniex bżonnu. In-nies u l-ħtiġijiet tagħhom huma wara kollox il-qofol tal-ippjanar serju. Imma sfortunatament il-pjan għal Paceville hu mibni fuq pedamenti differenti. Għax il-filosofija tal-pjan hu li l-art, il-ġebel, il-konkos u l-azzar jiġu qabel in-nies.

Din hi triq li twassal għal Gvern li jaħdmek biex jistagħnew l-ispekulaturi. Inti trid li pajjiżna jkompli miexi f’din it-triq?

Ippubblikat f Illum : il-Ħadd 9 t’Ottubru 2016

 

The Paceville Master Plan: a preliminary peek

paceville

 

In an event marking European Mobility Week, Transport Minister Joe Mizzi announced various initiatives which, if properly implemented would contribute to a reduction in the amount of congestion on our roads. Studies on the feasibility of a tram service, car-sharing and bike-sharing, as well as e-bike schemes are all welcome initiatives.

Barely 48 hours after Minister Mizzi had made his announcements, the Planning Authority published a draft Paceville master plan for public consultation which also contains a number of transport related initiatives. It is entitled Paceville. Malta’s prime coastal location. Development Framework. Given the almost simultaneous announcements, it is not known whether there was any consultation with the  Transport Ministry.

The proposed master plan seeks to establish parameters for the further development or redevelopment of Paceville in view of the high concentration of large-scale development projects in the area, most of which are still in the pipeline, including various proposals for the development of high-rise buildings. Readers will remember that, way back in 2008, a Professor Mir Ali from the University of Illinois at Urbana-Champaign USA had advised the then MEPA on the urban design strategy to be adopted when considering the future of tall buildings in Malta. (Tall Buildings: the advice ignored by the Maltese authorities TMIS, 26 June)

Professor Ali had then emphasised the need to draw up a master plan identifying and addressing the impacts of tall buildings.  This advice was ignored when the Floor Area Ratio policy was drawn up by the Planning Authority. Likewise, it was ignored regarding development proposals currently under consideration in Sliema – notably on the Tignè peninsula.

The Mott-Macdonald draft master plan for Paceville is a vindication of Professor Mir Ali’s advice. Professor Ali stressed that Malta needed to pull up its socks on issues of public transport, irrespective of whether high-rise buildings are developed or not. An efficient, integrated and sustainable public transport system is essential in under-pinning the essential infrastructure for tall buildings. Way back in 2008  Professor Mir Ali had emphasised that this must cover the whole of Malta and Gozo and should not be limited to just Paceville!

The Mott-Macdonald draft master plan puts forward three options through which it presents two contrasting transport strategies for public discussion. The first option, entitled Sustainable Transport Strategy seeks to reduce the dominance of the car and places considerable emphasis on the pedestrianisation of Paceville (including the pedestrianisation of coast), cycling facilities and bike sharing schemes, and seeks to ensure that  public transport is within easy reach – not more than a four-minute walk away.

The second option, aptly labelled Car-Based Transport Strategy defends the car’s dominance on our roads and puts the emphasis on reducing congestion by improving road intersections and better traffic management through an intelligent transport system and also proposes the introduction of a tunnel to be bored beneath Paceville. The third option, misleadingly labelled as the Balanced Transport Strategy, is a mixture of the first two options with the proposed tunnel shifted to the edge of Paceville.

The Mott-Macdonald draft strategy suggests that the third option is the preferred option.

During the coming six weeks (the length of the consultation period) we will have the opportunity to dissect the different transport strategies as well as the other proposals in the draft master plan. The draft is over 200 pages long and deals with various development, transport and infrastructural options of relevance to the various Paceville development proposals and is to be implemented over a number of years.

It is right and proper that the impacts of the extensive developments projected for Paceville are examined cumulatively and in a holistic manner. Such an attitude and methodology, if maintained throughout, can only lead to workable solutions that will benefit everyone’s.

It does, however, inevitably beg the question: why is all this applicable to Paceville but ignored in respect of the Tignè peninsula in Sliema, as well as elsewhere else?

published in the Malta Independent on Sunday, 25 September 2016