Gozo Channel: tunnelling discounts

discounts

 

When the current Gozo Channel tunnel debate was initiated around five years ago, the then Minister Chris Said went on record to emphasise that the proposed tunnel, to be bored under the seabed would cost approximately €150 million. This estimate has now been upped to €300 million.

This is one of the basic assumptions underlying the study commissioned by Transport Malta, together with the Gozo Business Chamber, and carried out by E Cubed Consultants Ltd, commonly referred to as the “economic and financial feasibility study”.

The study makes interesting reading as it considers the economics of the so-called permanent link between the islands of Gozo and Malta. I respectfully submit that the conclusions of this study are as valid as the basic assumptions which underpin it.

I draw the attention of readers to the fact that proposals for various tunnels are currently under consideration in other countries.

The first is the proposed Trans-Pennine tunnel, intended to improve the transport links between Sheffield and Manchester in the UK. The ambitious 18- mile (29km) tunnel would be built under the A628 Woodhead Pass. After having established that the geology of the Pennines was suitable for such a project, it was estimated that the approximate cost would be a staggering £6 billion (€8.40 billion).

The second UK project is the much-debated and controversial tunnel at Stonehenge. Intended to upgrade the A303 road, it is projected to have a length of 1.8 miles (2.9 km) and is currently estimated to cost £490 million (€700 million).

Another projected tunnel, recently given the green light, will pass between the Danish island of Lolland and the German island of Fehmarn. Construction work on this 19 km tunnel should start next January and it is estimated to cost €8.7 billion.

The estimates for the proposed tunnels in the United Kingdom indicate that the cost of a 10 km tunnel would exceed the €2 billion mark, even before taking into account the fact that excavating below the seabed would cost substantially more. In addition, the Danish/German tunnel indicates a pro-rata cost of €4.7 billion for a 10 kilometre tunnel.

In addition, the geological parameters below the Gozo Channel are still largely unknown: geological studies have to be carried out and examined in detail in order to establish the facts. Without these facts, the basic information necessary to take essential design decisions is still unavailable. What is known is worrying enough: the presence of active geological faults running right through the proposed route of the tunnel.

The study’s conclusions – that the proposed tunnel is economically viable – have  been reached prior to the carrying out of geological studies. Even the estimated costs used in the economic viability study have been established before these essential geological studies.

In this type of project, no estimate of costs can be precise – especially if it is not based on adequate and essential information.

This indicates that the conclusion of the economic viability study was premature.

In addition to the geological studies, additional important (and essential) studies have (as far as is known) not yet been commissioned. These include studies on the environmental impact, business impact and social impact.

Once concluded, such studies will inevitably point to other issues that will require detailed consideration, including the extent to which the projected permanent link between Malta and Gozo will toll the death knell for holiday accommodation in Gozo: hotels, flats and farmhouses.

The above indicates that, unless the promoters of the tunnel have some cast-iron guarantee of substantial discounts on the costs, the proposal is a non-starter even before any consideration of the environmental, business and social impact. It is about time to begin serious work on the practical alternative: a fast ferry service between Gozo and the Grand Harbour.

published in The Malta Independent on Sunday : 6 December 2015

Il-mina bejn Malta u Għawdex

Gozo_tunnel_route_alignment_options

 

Ma nafx jekk il-Ministru tal-Finanzi kienx jaf x’inhu jgħid meta qal li l-feasibility study “ikkummissjonat minn Transport Malta u l-Gozo Business Chamber” dwar il-mina bejn Malta u Għawdex kien lest. Imbagħad fis-sentenza ta’ wara jgħidilna li l-pass li jmiss issa huwa l-istudju tekniku u ġeoloġiku dwar il-mina.

Il-mistoqsija toħroġ waħedha: kif tista’ tagħmel feasibility study sura, jiġifieri studju dwar jekk jaqbilx li jsir il-proġett, meta għadek ma lestejtx l-iktar studju importanti: dak ġeoloġiku.

Dan ilu żmien jingħad minn kull min jaf l-affarijiet.

Jiena ktibt dwar dan kważi ħames snin ilu.

Iktar importanti milli ktibt jien, illum tkellem mat-Times il-ġeoloġista Peter Gatt. Tkellem ukoll mat-Times nhar it-3 ta’ Frar 2011.

Dr Peter Gatt jispjega fit-Times tal-lum għaliex qabel ma jsir l-istudju ġeoloġiku ma tista’ tikkonkludi xejn. Dan l-istudju hu “a vital first step”. Dan minħabba li l-istudju ġeoloġiku, jekk isir sewwa, jidentifika l-problemi ġeoloġiċi fuq ir-rotta li tkun ser titħaffer. Min-naħa l-oħra, jispjega Dr Gatt, jekk l-istudju ma jsirx, jew ma jsirx sewwa l-ispejjes tal-proġett jimmoltiplikaw. Kif ġara, jgħidilna Dr Gatt, fil-mina bejn Delimara u l-Marsa [bejn iż-żewġ power stations] li swiet id-doppju ta’ dak ippjanat minħabba li, billi ma kienx hemm informazzjoni ġeoloġika adegwata f’idejn min fassal il-proġett, kien hemm kollass tal-blat f’diversi partijiet tal-mina.

Dr Gatt isemmi l-eżempju tal-istudju ġeoloġiku li sar bi preparazzjoni għaċ-Channel Tunnel bejn l-Ingilterra u Franza. Dan l-istudju dam 50 sena biex sar u minkejja dan, l-ispiża taċ-Channel Tunnel xorta varjat bi 80% mill-istima oriġinali.

Meta wieħed iqis dan kollu ma nafx x’feasibility study sar!

Qalulna ukoll (mhux fil-baġit) li l-mina ser tiġi tiswa madwar €250 miljun. Meta tqis l-ispejjes li jistgħu jkunu meħtieġa minħabba l-kundizzjonijiet ġeoloġiċi taħt il-Fliegu bejn Malta u Għawdex, naħseb li din l-istima hi baxxa ħafna. Fil-fatt jiena fl-artiklu tiegħi tal-2011 kont għidt li probabbilment li l-ispiża tkun bejn €1 biljun u €1.5 biljun. Dan kont ibbażajtu fuq l-ispiża stmata għall-mina bejn il-gżira Daniża ta’ Lolland u l-gżira Ġermaniża ta’ Fehmarn li kienet qed tkun diskussa f’dak iż-żmien. Għalkemm dawn huma stimi imma xorta hemm diskrepanza kbira li mhiex ġustfikata.

Hemm dawn il-problemi kollha u għandna ma bdejniex nitkellmu dwar impatti ambjentali, li minnhom hemm bosta.

Il-mina, biex issir, ser tiġġenera kwantità kbira ta’ blat imqatta. Dan ivarja skond id-diżinn u jista’ jammonta sa żewġ miljun metri kubi ta’ blat. Hemm ukoll is-siti Natura 2000 li qegħdin viċin ħafna taż-żona fejn ser tiżbokka l-mina fl-inħawi taċ-Ċumnija limiti tal-Mellieħa.

Imma l-feasibility study lest, qalilna l-Ministru!

The right link that remains missing

The proposal by Franco Mercieca (Minding Our Gap, The Sunday Times, January 23) and Parliamentary Secretary Chris Said (Light At The End Of The Tunnel, The Times, January 31) to permanently link Malta and Gozo need to be considered in a strategic context.

Various proposals have been discussed throughout the years addressing Gozo’s double insularity. While the difficulties encountered by Gozitans to cross the channel are to be addressed it has to be underlined that if a permanent link is introduced it may have various other effects in addition to addressing mobility between the islands.

None of the proposals has assessed whether Gozo’s isolation is a positive feature, which, once lost, will never be regained.

Once Gozo is permanently linked with the mainland it will be an integral part of it, for better or worse. In particular, one would have to consider whether a permanent link would impact negatively the contribution of tourism towards the Gozitan economy.

Certainly, with an easier access, Gozitan consumers could tap the retail outlets of northern Malta. With Dr Said being responsible for consumer protection this could be an added bonus.

Whether the proposal is a bridge or a tunnel, a land based or an amphibious airplane. all come at a cost and leave considerable impacts. Costs are not just economic but social and environmental too.

A tunnel excavated below the seabed will undoubtedly eliminate visual intrusion into the Comino and Ċirkewwa landscape but it will certainly cause another rubble mountain resulting from excavating through at least six kilometres of rock under the seabed as well as additional kilometres to create the tunnel’s points of access on land. This rubble mountain could be anything between 1.5 and two million cubic metres of excavated rock depending on the actual design of the tunnel and its selected route.

The experience of various Nordic countries has been mentioned. At the time of writing a similar project has just been approved by the Danish Parliament to link the Danish island of Lolland to Fehmarn, a German island. Both islands are already linked through bridges to their respective countries. When finalised, this project would reduce the duration of a rail journey between Hamburg and Copenhagen by 33 per cent, from 4.5 hours to three hours. The tunnel will be 18 kilometres long. Works are projected to commence in 2014 and will take about six years to conclude. Costs are estimated to be in the region of 32 billion kroner, that is €4.2 billion. The projected tunnel across the Fehmarn strait will not be of the excavated type but prefabricated sections will be laid on the seabed.

The costs of these types of projects are indicative as there are a lot of variables involved. The Channel Tunnel between England and France, for example, overshot its final estimates based on actual designs by over 80 per cent.

Geologist Peter Gatt, commenting on The Times (February 3), pointed out that the Gozo Channel’s geology is riddled with faults. In addition, he pointed out there are areas of the seabed around Comino where clay abounds. This, it was pointed out, compounds the issue of expenses relative to civil engineering solutions, which have to be based on a thorough examination of the geology of the Gozo Channel.

There are a large number of caves in the areas. In addition, as pointed out by marine biologists, the Gozo Channel contains various marine protected areas.

On the basis of the above, it would seem the cost of the projected tunnel would be substantially higher than the €150 million guesstimate of Dr Said. The Fehmarn strait projected tunnel costings point towards an estimate of between €1 billion and €1.5 billion for the Gozo Channel tunnel, that is between six and 10 times the Said guesstimate. This estimate could become more precise when all the constraints, foremost being those of a geological and environmental nature, have been identified.

The government is unfortunately approaching the issue of identifying the suitable missing link between Malta and Gozo in a very amateurish and populist manner. It has so far failed to produce a strategy addressing the interlinking of transport between Gozo and the north of Malta. When such a strategy has been produced it should be subjected to a strategic assessment as laid down by the Strategic Environment Assessment Directive of the European Union. The social, environmental and economic impacts of the various options on both Malta as a whole and Gozo as a region would thus have been identified and analysed.

The necessary decision can then be taken in the interest of the whole community.

It has to be clear to all that if we are to arrive at a solution in identifying the suitable missing link the populist approach utilised so far should be discarded.

Published in The Times of Malta, February 12, 2011