Il-mina mhix soluzzjoni: hi problema

Il-mina li hi proposta taħt qiegħ il-baħar bejn Għawdex u Malta ser ikollha impatti negattivi konsiderevoli kemm fuq Għawdex kif ukoll fuq Malta. L-iżjed wieħed ovvju hu l-ġenerazzjoni ta’ madwar miljun u nofs metru kubu ta’ radam li ser jispiċċa fil-baħar. Dan ser jagħti bidu għal ħmar il-lejl ambjentali ieħor: għax l-iżviluppaturi ma baqgħalhomx fejn “jiżviluppaw” fuq l-art! Qed ifittxu l-ispazju. L-Awtorità dwar l-Ambjent u r-Riżorsi diġa identifikat fejn dan jista’ jsir. Mhux ta’ b’xejn li r-residenti tax-Xgħajra qed jirvellaw.

Il-problemi assoċjati mal-mina proposta huma bosta. Art agrikola madwar il-punti tad-dħul, fuq iż-żewġ naħat, kemm f’ Ta’ Kenuna fil-limiti tan-Nadur kif ukoll ħdejn

L-Għerien fil-periferija tal-Mellieħa u ma tul il-wied tal-Pwales ser ikollha tagħmel il-wisgħa. Din ser tispiċċa tkun trasformata f’toroq kif ukoll f’faċilitajiet għall-kontroll tad-dħul fil-mina. Magħhom imbagħad jiżdiedu pompi tal-petrol, kull naħa tal-mina.

Hu ċar, minn dak magħruf s’issa, li d-dħul għall-mina min-naħa ta’ Malta ser ikun viċin ħafna tal-ilma tal-pjan tal-Miżieb, jekk mhux dritt minn ġo fih ukoll! Dan l-ilma tal-pjan hu f’kundizzjoni tajba, l-aħjar wieħed fil-gżejjer Maltin. Din kienet ukoll waħda mir-ragunijiet ewlenin l-għaliex fil-passat riċenti kellhom ikunu abbandunati żewġ proġetti kbar fl-inħawi, dak tal-golf course u ieħor konness mat-toroq (in-network TEN-T).

Għandu jingħad ukoll li volum kbir ta’ traffiku ser ikun iġġenerat u dan ser jgħaddi viċin ħafna tar-riżerva naturali tas-Simar fix-Xemxija. Il-ħsejjes, id-dwal u t-tniġġiż tal-arja ser ikollhom impatt negattiv konsiderevoli fuq ir-riżerva, b’mod partikolari matul il-lejl, ħin li fih in-natura ukoll tfittex li tistrieħ.

Dawn il-problemi li inevitabilment jinħolqu mill-mina għandhom iwasslu lil min hu rasu fuq għonqu biex ifittex soluzzjoni alternattiva biex titjieb il-konnettività bejn Għawdex u Malta. Soluzzjoni li tevita dawn il-problemi u iktar.

Ħa nkun ċar: il-konnettività bejn il-gżejjer ta’ Għawdex u Malta teħtieġ titjib konsiderevoli: is-soluzzjoni imma, mhiex il-mina. Is-soluzzjoni għandha tkun waħda li tiffaċilita l-moviment bejn il-gżejjer mingħajr ma żżid mal-problemi li diġa għandna. B’mod partikolari għandna nevitaw li nkabbru l-problema tat-traffiku iktar milli hi diġa. Dan nistgħu nagħmluh jekk niżviluppaw soluzzjoni li tnaqqas flok ma tkabbar id-dipendenza tagħna fuq il-karozzi.

Hu stmat li l-mina proposta ser iżżid il-medja kull jum tal-movimenti tat-traffiku bejn il-gżejjer mit-3000 tal-lum għal madwar 9000: żieda bi tlett darbiet fuq perjodu ta’ ħmistax-il sena. Wieħed ma jridx wisq għerf biex jifhem dawn iċ-ċifri, li nsibuhom ukoll fl-istudju ekonomiku kkummissjonat fl-2015 mill-Awtorità tat-Trasport u l-Kamra tal-Kummerċ Għawdxija. Għax il-ħlas biex tgħaddi mill-mina ser jinġabar minn fuq kull karozza u allura d-dħul ser jiddependi mill-ġenerazzjoni tal-ikbar ammont possibli ta’ traffiku. L-eżistenza tal-mina tiddependi fuq dan: bla traffiku ma tistax teżisti. Dan imur kontra l-oġġettiv ewlieni tal-Pjan Nazzjonali tat-Trasport (National Transport Master-Plan 2025) li fi kliem mill-iktar ċar jispjega kemm it-tnaqqis tal-karozzi mit-toroq tagħna hu l-mira fit-tul tal-politika tagħna dwar it-trasport.

Is-soluzzjoni meħtieġa trid tindirizza l-moviment tan-nies u mhux il-moviment tal-karozzi. L-unika soluzzjoni raġjonevoli allura hi l-introduzzjoni ta’ katamaran (fast ferry service) bejn Għawdex u Malta: bejn l-Imġarr f’Għawdex u punti varji mal-kosta f’Malta li jistgħu jinkludu x-Xemxija, Tas-Sliema u l-Belt Valletta. Ma dan imbagħad ikun hemm ħtieġa tat-titjib tas-servizz tat-trasport pubbliku minn fejn jieqaf il-katamaran għall-bqija tal-pajjiż.

Hu essenzjali li s-soluzzjonijiet li nagħżlu għall-problemi tagħna tat-trasport ikun jħarsu fit-tul ħalli nnaqqsu u mhux inżidu l-problemi li nħallu lil ta’ warajna.

Ippubblikat f’Illum: il-Ħadd 3 ta’ Frar 2019

Advertisements

The proposed Tunnel is not a solution: it is a problem

The proposed tunnel below the seabed linking Malta and Gozo will have considerable negative impacts on both Gozo and Malta. The most obvious one is the generation of around one and a half million cubic metres of bits of rock which will be dumped into our seas, kick-starting another environmental nightmare, land reclamation. The construction lobby has run out of space to “develop” on land. The Environment and Resources Authority has already started identifying potential sites. The residents of Xgħajra have good reason to be up in arms.

The problems associated with the proposed tunnel are manifold. Agricultural land around the two points of exit of the proposed tunnel will be gobbled up: at Ta’ Kenuna on the outskirts of Nadur, and close to L-Għerien, on the periphery of Mellieħa and further along the Pwales valley. This agricultural land will make way for the roads and toll-control facilities leading to the tunnel. Then, they will inevitably be complemented by more petrol stations.

On the basis of what is known so far, it is already clear that on the Malta side the tunnel will be bored through or very close to the Miżieb aquifer, which is still in a very good state – the only one on the island so graded. This fact has been one of the determining issues leading to the abandonment of other large scale projects in the area (the golf-course and part of the TEN-T network).

One could also add that a substantial amount of traffic will be channelled very close to the Simar Nature Reserve in Xemxija. The resulting noise, light and air pollution will have a considerable negative impact on the reserve, especially at night, a time when nature seeks its resting time.

The problems generated by the proposed tunnel are substantial. There is, however, a reasonable solution to the connectivity issue.

Let me be clear: connectivity between the islands of Gozo and Malta needs considerable improvement. The proposed tunnel, however, is not the solution. The solution should be one which facilitates movement between the islands without creating more problems than we already have! In particular, we should avoid worsening the traffic problem. This can be done if the solution we seek is not one which increases our car dependency.

It is estimated that the proposed tunnel will increase average daily traffic movements between the two islands from the current 3,000 to a projected 9,000 – a threefold increase estimated over a fifteen-year period. One immediately understands the purpose of these projections referred to in the feasibility study commissioned jointly by Transport Malta and the Gozo Business Chamber in 2015. The toll to be charged – and, consequently, the tunnel’s economic performance – is dependent on generating the maximum traffic possible. Traffic underpins the very existence of the tunnel. This runs counter to the basic objective of the National Transport Master-Plan 2025 which in crystal clear language spells out the reduction of cars from our roads as the long-term objective of Malta’s National Transport Policy.

The solution needs to address the movement of people between the islands, not the movement of cars. The only reasonable solution would be the introduction of a fast-ferry service between Gozo and Malta, between Mġarr in Gozo and various points in Malta, which would include Xemxija, Sliema and Valletta. This should be linked to an improvement in the public transport links between these points and the rest of the country.

It is essential that we seek long-term solutions to our transport problems, such that we do not leave future generations burdened by our problems.

published in The Malta Independent on Sunday – 3 February 2019

L-ispekulaturi tal-art mgħejjuna mill-Gvern: ħa jaħtfu l-baħar ukoll

Qieshom mejtin bil-ġuh. Wara li ħarbtu l-art, issa ser iduru għall-baħar. Għalissa qed jillimitaw ruhom mir-Rikasli saż-Żonqor. Imma wara jibqgħu għaddejjin sa Baħar iċ-Ċagħaq.

Hu ċar daqs il-kristall li l-ispekulaturi tal-art lokali dawwru għajnejhom lejn il-kosta tagħna biex jissodisfaw ir-regħba tagħhom bla qies.

L-informazzjoni li l-Awtorità għall-Ambjent u r-Riżorsi (ERA) identifikat il-kosta bejn ir-Rikażli u iż-Żonqor bħala l-iktar parti tal-kosta li hi addattata għar-riklamazzjoni hi ta’ tħassib kbir. L-ERA qed tgħid li għaliex iż-żona hija diġa’ iddegradata (jiġifieri prattikament mejta), allura ma jimpurtax li tkompli issirilha aktar u aktar ħsara, għax daqslikieku ma baqax tama għal din iż-żona. Hekk qed tgħid l-ERA b’ħafna logħob bil-kliem.

Għalkemm għadha ma ttieħdet l-ebda deċiżjoni definittiva, l-identifikazzjoni mill-ERA ta’ din iż-żona hija r-riżultat ta’ pressjoni biex jinstab sit adattat għar-rimi ta’ skart tal-kostruzzjoni li jirriżulta minn proġetti fuq skala kbira bħall-mina proposta bejn Malta u Għawdex, kif ukoll il-proġett dB fis-sit tal-ITS u l-proġett Corinthia fuq il-peniżola ta’ Pembroke. Dawn il-proġetti se jipproduċu madwar miljun u nofs metru kubu ta’ skart tal-kostruzzjoni.

Iż-żona matul il-kosta tax-Xgħajra diġà ntużat bħala sit għar-rimi tal-iskart tal-kostruzzjoni minn proġetti oħra kbar, bħall-proġett mostru tal-MIDI fuq il-peniżola ta’ Tigne. Hi żona li ġiet wkoll effetwat bħala riżultat tal-outfall tad-drenaġġ tul is-snin.

Il-Gvern irċieva madwar għoxrin espressjoni ta’ interess, liema sejħa ħarget mill-Gvern innifsu, għal proġetti li jinvolvu r-riklamazzjoni tal-art f’diversi partijiet tal-kosta. Deċiżjonijiet dwar dawn il-proġetti għadhom pendenti. Huwa magħruf ukoll li fost l-aktar proġetti msemmija huma dawk bejn Portomaso u Baħar iċ-Ċagħaq. Fosthom hemm it-talba riċenti relatata mal-proġett Corinthia fuq il-peniżola ta’ Pembroke kif ukoll iż-żona marbuta ma’ Portomaso li kienet tifforma parti mill-Masterplan ta’ Paceville li illum suppost li ġie skartat.

Sfortunatament il-Gvern huwa favur ir-riklamazzjoni tal-art u għalhekk id-dikjarazzjonijiet minn uffiċjali tal-gvern li jipprovaw jitfgħu l-ballun f’saqajn l-ERA mhux kredibbli.

Alternattiva Demokratika hi kontra l-estensjoni tal-kankru tal-ispekulazzjoni tal-art għal fuq il-baħar tagħna. Tħeġġeġ lill-Gvern biex jieħu miżuri effettivi biex jipproteġi l-kosta u l-aċċess għaliha. Għad hemm diversi talbiet pendenti minn NGOs ambjentali għall-protezzjoni tal-kosta u dan in konnessjoni mal-implimentazzjoni tal-ligi tad-dimanju pubbliku. Kemm se jdumu fuq l-ixkaffa dawn it-talbiet?

Central Link Project u l-Istudji Ambjentali

Sirna nafu li l-istudji dwar l-impatti ambjentali tal-proġett tat-toroq magħruf bħala Central Link Project lesti.

S’issa, dawn l-istudji għadhom mhumiex pubbliċi, u, fil-fatt, fil-mument li qiegħed nikteb ma hemm l-ebda informazzjoni fuq dawn l-studji fuq is-sit elettroniku tal-ERA, l-Awtorità dwar l-Ambjent u r-Riżorsi.

Imma, minn dak li ntqal s’issa minn uffiċjali f’isem Infrastruttura Malta l-problema b’dawn l-istudji ser tkun mhux daqstant dwar dak li jgħidu imma dwar dak li jħallu barra. Imma dwar dan inkun nista’ nitkellem aħjar meta r-rapporti jkunu ppubblikati għall-konsultazzjoni pubblika, kif hemm l-obbligu li jsir bil-liġi. Il-konsultazzjoni pubblika normalment tkun twila sitt ġimgħat imma tista’ tkun itwal ukoll.

Alternattiva Demokratika diġa tkellmet ċar dwar dan il-proġett inutli li ser ikompli jżid il-karozzi u (l-ħsara ambjentali) fit-toroq tagħna.

Il-posizzjoni ta’ Alternattiva Demokratika hi ċara daqs il-kristall: il-proġett imur dijametrikament kontra l-pjan nazzjonali tat-Trasport li fassal u approva l-Gvern: pjan li jrid inaqqas il-karozzi mit-toroq.

Kif ikollna ċans naraw l-istudji, hekk kif dawn ikunu pubblikati, nkunu nistgħu nitkellmu aħjar.

Il-mina t’Għawdex: ħmar il-lejl

Il-Ministru Ian Borg, iktar kmieni din il-ġimgħa, infurmana li kien qed jaħdem biex iwettaq il-ħolma ta’ diversi Għawdxin billi jmexxi l-quddiem il-proċess tal-mina taħt qiegħ il-baħar bejn Malta u Għawdex. Wara dibattitu li ilu għaddej is-snin hu ċar li iktar milli jwettaq il-ħolm ikun aħjar jekk Ian Borg jipprepara ruħu għal ħmar il-lejl.

Saru studji ġejoloġiċi imma lanqas il-konklużjonijiet ġenerali dwarhom ma nafu. Għadhom mistura qieshom xi sigriet tal-istat. Tliet snin ilu l-ġejoloġista Peter Gatt kien ġibed l-attenzjoni għall-fatt li l-mina tal-Enemalta bejn il-power station tal-Marsa u Delimara kienet swiet id-doppju ta’ dak ippjanat u dan minħabba kollass tal-blat f’diversi punti matul il-mina nnifisha. Dan kien seħħ bħala riżultat tan-nuqqas ta’ informazzjoni ġejoloġika meta ġiet imfassla l-mina. Kieku dan kellu jseħħ waqt li jkun għaddej ix-xogħol fuq il-mina bejn Malta u Għawdex hu inevitabbli li jkollna problemi kbar, inkluż possibilment numru ta’ mwiet.

Hu fatt magħruf li fil-Fliegu hemm diversi kisriet ġejoloġiċi (geological faults). Tajjeb li nirrealizzaw li tnejn mill-proposti għall-mina, li saru minn Mott MacDonald, il-konsulenti ta’ Transport Malta, jgħaddu minn dawn il-kisriet.

Li jkunu eżaminati l-kampjuni tal-blat f’laboratorju, anke jekk għal ftit ġimgħat, bla dubju jżid l-għarfien tal-ġejoloġija taż-żona imma dan mhux biżżejjed biex fuqu jittieħdu deċiżjonijiet dwar id-diżinn tal-proġett. Biżżejjed nifhmu li minkejja l-istudji ġejoloġiċi dettaljati fuq numru kbir ta’ snin, ix-xogħol fuq il-mina bejn l-Ingilterra u Franza, iċ-Channel Tunnel, kellu jieqaf u jkun devjat diversi drabi minħabba li t-tħaffir iltaqa’ ma problemi ġejoloġici li ma kien hemm l-ebda indikazzjoni tagħhom fl-istudji dettaljati!

L-istudji serji jieħdu ż-żmien biex isiru: ma jistgħux ikunu mgħaġġla minħabba data determinata minn agenda politika.

Tliet snin ilu, Transport Malta, flimkien mal-Kamra tal-Kummerċ Għawdxija kkummissjonaw studju ekonomiku, ferm qabel ma biss bdew l-istudji ġejoloġiċi. L-istudju kien intitolat Establishing a Permanent Link between the Island of Gozo and Mainland Malta: An Economic Cost Benefit Analysis of Available Strategic Options, li kien sar minn E-Cubed Consultants. Dan l-istudju kien argumenta li t-traffiku bejn il-gżejjer kien ipproġettat li fuq perjodu ta’ 15il sena jiżdied minn medja ta’ 3000 moviment kuljum għal 9000 moviment kuljum. Argument li jmur kontra l-Pjan Nazzjonali għat-Trasport approvat fl-2015 ukoll.

Il-mina proposta teħtieġ ammont kritiku ta’ movimenti ta’ karozzi li jħallsu biex jgħaddu mill-mina u per konsegwenza minn fuqhom jinġabru l-ispejjes tal-mina kif ukoll il-profitti tal-operaturi. Fi ftit kliem il-mina, biex tirnexxi tiddependi minn moviment kbir ta’ karozzi kuljum. Dan imur kontra l-politika dwar it-trasport tal-lum, li ta’ l-inqas fuq il-karta, timmira għal tnaqqis ta’ karozzi mit-toroq tagħna. Din hi materja li bla dubju għandha tkun eżaminat mill-istudju fuq l-impatti ambjentali (EIA) dwar il-mina proposta. Dan l-istudju għadu fl-istadji inizzjali tiegħu u dan wara li l-Awtorità dwar l-Ambjent u r-Riżorsi ftit ġimgħat ilu approvat dak li għandu jkun indirizzat (terms of reference) minn dan l-istudju. L-EIA hu stadju essenzjali li minnu jeħtieġ li jgħaddi l-proġett.

Għaldaqstant, kien irresponsabbli l-Ministru tat-Trasport, meta, iktar kmieni din il-ġimgħa, ħabbar li fi żmien sitt xhur kienet ħierġa sejħa internazzjonali għall-offerti għall-mina bejn Malta u Għawdex. Dan ifisser li dawn l-istudji huma irrelevanti? Fl-opinjoni tiegħi il-Ministru  qiegħed jagħti  dan il-messaġġ ċar u tond.

Din hi l-agħar forma ta’ governanza ħażina għax jimmina l-isforzi tal-awtoritajiet fil-qadi ta’ dmirijiethom. B’dan il-ħsieb jiena ktibt lill-Ombudsman u tlabtu jinvestiga dan in-nuqqas ta’ governanza tajba. Il-Gvern għandu jkollu l-paċenzja li jistenna sakemm ikunu konklużi l-istudji ambjentali qabel ma jieħu d-deċiżjonijiet.

 

Ippubblikat fuq Illum : Il-Ħadd 16 ta’ Diċembru 2018

Gozo tunnel nightmares

Minister Ian Borg informed us, earlier this week, that he seeks to turn into reality a Gozitan “long-held dream” by starting the process for a Malta-Gozo tunnel below the seabed. After debating the matter for years, it is clear that rather more than dreams, Ian Borg should prepare himself for a nightmare.

Geological studies have now been carried out and the results therof are being treated as some state secret. Three years ago, geologist Peter Gatt had drawn attention to the fact that the Enemalta tunnel between the Marsa power station and Delimara had a cost overrun of 100 per cent as a result of rock collapse along several points of the tunnel. This had occurred due to inadequate geological information fed into the design process. If the same were to happen during the Malta-Gozo tunnel works, a series of disasters, including possibly loss of life, would be inevitable.

It is a known fact that the Gozo channel is full of geological faults. It is pertinent to note that two of the tunnel options put forward by Transport Malta advisors Mott MacDonald pass through an active fault in the Gozo channel.

Taking borehole samples and examining them in a laboratory over a few weeks certainly increases our knowledge of the geology of the area but it is nowhere near the sufficient knowledge on the basis of which one can conclude the design parameters of the project. Suffice it to point out that notwithstanding the detailed geological studies spanning over many years and underpinning planning for the Channel Tunnel linking Folkestone in Kent and Coquelles near Calais, the drilling of the tunnel had to be deviated at certain points because of unpredicted geological formations.

Serious studies take years to conclude: they cannot be rushed to meet a deadline set by a political agenda.

Feasibility studies have been carried out some time ago, long before the geological studies were even taken in hand. Three years ago, the Gozo Business Chamber in conjunction with Transport Malta commissioned a study entitled Establishing a Permanent Link between the Island of Gozo and Mainland Malta: An Economic Cost Benefit Analysis of Available Strategic Options. In the study, which was carried out by E-Cubed Consultants, it was argued that the average annual daily traffic (AADT) between the islands is projected to increase from 3000 to 9000 vehicle movements over a 15-year period.

This feasibility study makes assumptions which run counter to the National Transport Master Plan objective of reducing cars from our roads.

Basically, the proposed tunnel requires a critical mass of vehicular movements which would be subject to the payment of a toll and hence contribute to the recovery of the capital outlay, maintenance costs and profits. This runs counter to current Maltese Transport policy, which (at least on paper) aims to reduce the use of private cars from our roads.

This is an issue which would undoubtedly be examined by the Environmental Impact Assessment (EIA) on the proposed Tunnel which study is currently in its initial stages after the Environment and Resources Authority recently approved the terms of reference of such a study. The EIA is an essential stage of the assessment of the project.

It was therefore irresponsible for the Minister of Transport, earlier this week, to announce that within six months an international call for tenders would be issued relative to the Malta-Gozo undersea Tunnel. Does this mean that the government considers the EIA irrelevant? This, in my opinion is the clear message being conveyed.

It is the worst form of bad governance as it undermines the efforts of the established authorities in carrying out their responsibilities. With this in mind, I have written to the Ombudsman and asked him to investigate this breach of good governance. Government should have the patience of awaiting the outcome of the EIA before taking any further decisions.

published in The Malta Independent on Sunday : 16 December 2018

Ktibt lill-Ombudsman dwar il-mina bejn Malta u Għawdex

 

Għadni kif, madwar siegħa ilu tajt ittra lill-Ombudsman biex jiftaħ investigazzjoni dwar il-mina bejn Malta u Għawdex.

Il-bieraħ il-Ministru Ian Borg ħabbar li fi żmien sitt xhur oħra ser joħroġ it-tender dwar il-mina taħt qiegħ il-baħar bejn Malta u Għawdex. Dan għamlu minkejja li l-istudju dwar l-impatti ambjentali (EIA) li dwaru s’issa ġiet konkluża biss il-konsultazzjoni pubblika dwar it-Terms of Reference għadu bil-kemm beda.

Apparti li dan hu l-ikbar diżrispett lejn l-Awtorità tal-Ambjent u r-Riżorsi da parti tal-amministrazzjoni pubblika tal-pajjiż, din id-dikjarazzjoni tal-Onorevoli Ministru hi ukoll indikazzjoni ċara ta’ nuqqas ta’ governanza tajba u twassal il-messaġġ ċar li l-proċess ta’ studju tal-impatti ambjentali hu meqjus bħala wieħed irrelevanti u li qed isir għalxejn għax id-deċiżjonijiet lesti irrispettivament minn dak li jista’ jirriżulta mill-istudji.

Fil-dawl ta’ dan għan-nom ta’ Alternattiva Demokratika jiena dal-għodu tlabt lill-Ombudsman biex jinvestiga u jieħu dawk il-passi li jidhirlu meħtieġa.

Ma nistgħux nibqgħu sejrin hekk. Kif nippretendu lin-nies jagħtu kaz u jsegwu il-liġi, jekk il-Ministru b’imġiebtu jiġi jaqa’ u jqum?

The drummer’s call

The drummer was floored. A photo on the social media depicted a drum departing from the hand of a uniformed policeman and flying in the direction of the floored drummer.

Last Thursday’s protest by Moviment Graffiti and Kamp Emergenza Ambjent was not about the pending decision on the proposed fuel service station at Bulebel in Żejtun. It was rather about the lethargy of the authorities in considering the overhaul of the Fuel Service Stations policy.

The mishandling of the protestors by the police apparently marks a new season: it has been ages since the police force was so employed in Malta. Apparently, the authorities are getting very itchy.

Appreciation of the environment is limited to clean-up days subject to the media’s glare, with the remaining days of the year being a free-for-all. There is nothing new in such an attitude. We have been facing it year-in, year-out for a considerable time. By now we are accustomed to greenwashing and some of us have developed an acute allergy to the authorities’ greenwashing.

Playing on the drum, the drummer was announcing to one and all that we are all fed up by the authorities’ procrastination and that it was about time that they realised that this is another case of abuse of authority and maladministration. The Republic belongs to everyone and not just to the privileged few.

The number of pending applications for fuel service stations is considerable, notwithstanding the fact that we do not need even one of them. The long-term policy direction is to reduce our dependency on private cars. In addition, as indicated by the Prime Minister around twelve months ago, we are awaiting the announcement of the cut-off date when the remaining cars on our roads are primarily electrically driven.

It has been repeatedly emphasised that the 3,000 square metres permissible footprint that the Fuel Service Station policy allows for the development of fuel service stations outside the development zone is excessive and the proposal by the Environment and Resources Authority to reduce this footprint to 2,000 square metres is not much of an improvement. If a fuel service station is required its footprint could be substantially less. Obviously, this would necessitate doing away with all the ancillary commercial activity at ODZ fuel service stations that the current fuel service station policy introduced in reaction to those seeking pastures new for their “investments”. The current policy gives more weight to ensuring a return on investment than to the need to protect our countryside from further rape.

Last Thursday, the Planning Authority Board turned down the application for a fuel service station at Bulebel in Żejtun. There are other applications pending, most of which will be eventually approved. This will be done notwithstanding the fact that there is no need for more fuel service stations. We have more than enough of them and it is certainly about time that we start closing some of the existing ones.

In my article last week, I emphasised that we need to implement the vision put forward by the National Transport Master Plan 2025 which advocates the need to reduce our dependency on cars. The need to overhaul the Fuel Service Station Policy has to be considered in this context. If we need to reduce (drastically) the number of cars on our roads, it follows that we do not need any more fuel service stations.

In the coming weeks the drummer’s call through more rhythmic movements of the drum sticks will be required to alert us to more sessions of the Planning Authority Board which will be convened to approve the further rape of our countryside.

published in The Malta Independent on Sunday – 16th September 2018

Il-mina bejn Malta u Għawdex: il-qerda finali t’Għawdex wara l-bieb

Nhar l-Erbgħa festa pubblika. Hi ukoll id-data tal-egħluq għall-konsultazzjoni pubblika li qed tagħmel l-Awtoritá tal-Ambjent u r-Riżorsi (ERA) fuq it-termini ta’ referenza għall-istudju dwar l-impatt ambjentali (EIA) tal-mina proposta bejn Malta u Għawdex.

Is-sit elettroniku tal-ERA jippreżenta żewġ dokumenti sabiex jassistu lil dawk li qed jipparteċipaw f’din il-konsultazzjoni pubblika. Dawn id-dokumenti jispjegaw il-proposta u jidentifikaw numru ta’ fatturi li jistgħu jkunu jeħtieġu investigazzjoni, u dan biex dawk li jieħdu d-deċiżjoni jkunu megħjuna jagħmlu l-“aħjar” għażla.

F’dawn id-dokumenti hemm numru ta’ nuqqasijiet li jistunaw u juru kemm Transport Malta tiġi taqa’ u tqum mill-wirt ambjentali tagħna.

Transport Malta tibbaża l-proposti tagħha fuq ir-rapport ta’ Mott MacDonald, datat Marzu 2012 u intitolat: Preliminary Analysis: Assessment of Road Tunnel Options between Malta and Gozo. Wara li kkunsidrat erba’ proposti differenti għall-mina kif imfisser fir-rapport ta’ Mott MacDonald, Transport Malta ddeċidiet li tagħżel il-proposta numru 4 b’emenda: hi proposta li tkun tikkonsisti f’mina waħda b’żewġ karreġjati u tibda mill-inħawi taħt Ta’ Kenuna fin-Nadur Għawdex u tispiċċa fl-Imbordin biswit il-Wied tal-Pwales f’San Pawl il-Baħar.

Fid-dokumenti jgħidulna li l-ewwel tliet proposti kienu skartati għax setgħu jikkawżaw ħsara ambjentali sostanzjali, f’qiegħ il-baħar jew lir-riżerva naturali tal-Għadira. Imma la Transport Malta u l-anqas l-ERA ma ħassew il-ħtieġa li jgħidulna fid-dokumenti li ippubblikaw li meta ntagħżlet il-proposta numru 4 u ġġebbdet sal-Imbordin biswit il-Wied tal-Pwales din ġiet viċin wisq tar-riżerva naturali l-oħra, tas-Simar, u tgħaddi dritt mill-Miżieb, mal-pjan tal-ilma.

Ir-riżerva naturali tas-Simar hi sit ikklassifikat bħala Natura 2000 tal-UE, u l-pjan tal-ilma tal-Miżieb hu l-unika wieħed sura li fadlilna. Allura hemm il-possibilitá kbira li din il-proposta għal mina tmur kontra żewġ direttivi importanti tal-Unjoni Ewropea: id-Direttiva Qafas dwar l-Ilma u d-Direttiva dwar il-Abitat.

Fl-2015 il-medja ta’ movimenti ta’ karozzi bejn Malta u Għawdex, kif jirriżulta mill-istatistika uffiċjali, hi ta’ madwar 3000 kuljum. Id-diversi studji u rapporti ppubblikati sal-lum jikkalkulaw li l-mina, meta tkun lesta, tista’ twassal sabiex in-numru ta’ karozzi li jaqsmu bejn iż-żewġ gżejjer jitla’ bejn 9000 u 10000 kuljum. Gordon Cordina minn Ecubed fir-rapport tiegħu kkummissjonat minn Transport Malta u l-Kamra tal-Kummerċ Għawdxija jindika li ser tintlaħaq iċ-ċifra ta’ 9000 karozza kuljum, fil-waqt li r-rapport Mott MacDonald jipponta lejn l-10,000 karozza kuljum.

Din iż-żieda konsiderevoli fil-moviment ta’ karozzi teħtieġ li tkun analizzata fil-kuntest tal-politika kurrenti dwar it-trasport. Il-master plan dwar it-trasport addottat mill-Gvern preżenti u ffinanzjat mill-Fond Ewropew għall-Iżvilupp Reġjonali hu ċar. Dan il-pjan jgħid li matul l-għaxar snin li fih ser ikun effettiv (2016-25), wieħed mill-oġġettivi ewlenin tal-politika tat-trasport f’Malta hi emfasi fuq l-użu ta’ mezzi alternattivi għall-karozzi privati u li fil-gżejjer Maltin jonqos l-użu tal-karozza privata.

Mela Transport Malta, għan-nom tal-Gvern Malti fl-2016, tistabilixxi politika dwar it-trasport biex tkun indirizzata l-konġestjoni tat-traffiku billi tinkoraġixxi bdil fl-imġieba favur mobilitá sostenibbli, u mbagħad toħroġ bi proposti bħal dawn tal-mina bejn Malta u Għawdex, li biex jagħmlu sens, jirrikjedu żieda enormi fit-traffiku.

Id-dokumenti fuq is-sit elettroniku tal-ERA għall-informazzjoni ta’ dawk li jridu jipparteċipaw f’din il-konsultazzjoni pubblika dwar il-mina bejn Malta u Għawdex jinjoraw kompletament il-politika dwar it-trasport.

Din hi s-sitwazzjoni li għandna illum. Drajna b’awtoritá tal-ippjanar sinkronizzata mal-lobby favur l-iżvilupp. Sfortunatament jidher li l-Awtoritá dwar l-Ambjent u r-Riżorsi miexja fuq l-istess passi. Il-jiem huma magħduda. Bla dubju dan ser iwassal għall-qerda ta’ Għawdex ukoll.

 

Ippubblikat fuq Illum : Il-Ħadd 12 t’Awwissu 2018

The Malta-Gozo tunnel: the final countdown to Gozo’s plunder starts now

Next Wednesday is a public holiday. It is also the closing date of the public consultation being carried out by the Environment and Resources Authority (ERA) on the terms of reference for the Environmental Impact Assessment (EIA) to be carried out on the proposed Malta-Gozo tunnel.

The ERA website presents two documents to assist those participating in the public consultation. These documents explain the proposal and highlight a number of issues that will require further investigation in order to assist the decision-takers in choosing for the “optimum” solution.

There is a number of glaring deficiencies in these documents which indicate the contempt that Transport Malta has for our environmental heritage.

Transport Malta bases its proposals on the Mott MacDonald Report of March 2012 entitled: Preliminary Analysis: Assessment of Road Tunnel Options between Malta and Gozo. After considering the four options for a tunnel as resulting from the Mott MacDonald report, Transport Malta opted for an amended version of option number 4 which is proposed as consisting of a single bore two lane tunnel between the area below Ta’ Kenuna in Nadur, Gozo and L-Imbordin along the Pwales Valley in St Paul’s Bay in Malta.

We are told in the published documentation that the first three options were discarded because they could be the cause of considerable environmental damage to the seabed, as well as to the Għadira Nature Reserve. However, neither Transport Malta nor the ERA considered it appropriate to mention that the selected option, an amended option 4, stretches the Malta portal of the proposed tunnel to the Pwales valley very close to the Simar Nature Reserve and right through the Miżieb perched aquifer.

The Simar Nature Reserve is an EU Natura 2000 site, while the Miżieb perched aquifer is the only part of our water table that is still in a relatively good state. Consequently, two important EU Directives will most probably be infringed: The Water Framework Directive and the Habitats Directive.

Based on NSO statistics, in 2015 average number of daily vehicular crossings between Malta and Gozo was around 3,000. The various studies and reports published to date indicate that it is estimated that a tunnel between the two islands would trigger an increase to between 9,000 and 10,000 vehicle crossings daily. Gordon Cordina of Ecubed in his report commissioned by Transport Malta and the Gozo Business Chamber indicates a 9,000-daily mark, while Mott MacDonald points towards the 10,000 mark.

This considerable increase in vehicular movements needs to be analysed in terms of current transport policy. The Transport Master Plan, adopted by the current government and funded by the European Regional Development Fund, is very clear. It lays down that during its 10-year lifespan (2016-25) it will be an operational objective of transport policy in Malta to aim to provide alternatives to the use of private vehicles and to reduce the role of the private car as a means of transport in the Maltese Islands.

So, Transport Malta, on behalf of the Maltese government, spells out transport policy in 2016 aimed at addressing traffic congestion in Malta by encouraging a modal shift towards sustainable mobility. Yet it then comes out with proposals such as the Malta-Gozo Tunnel, which can only be feasible if there is an astronomical increase in vehicular traffic on our roads.

The documents placed by the ERA on its website to feed the public consultation process on the proposed Malta-Gozo tunnel ignore transport policy altogether.

This is the current state of affairs. By now we are accustomed to having a Planning Authority acting in synch with the development lobby. Unfortunately, it seems that the Environment and Resources Authority is closely following in its footsteps. The final countdown is on. It will inevitably lead to the plunder of Gozo as well.

Published in The Malta Independent on Sunday : 12 August 2018