L-inkompetenza, ħsara biss tagħmel

L-impjant f’Ħal-Far għall-ipproċessar tal-fdalijiet tat-tonn kellu l-potenzjal li jagħti kontribut sostanzjali għall-iżvilupp tal-ekonomija ċirkulari f’Malta. Bħal ħafna affarijiet oħra l-inkompetenza qerditu.

Fuq il-karta kien proġett tal-ogħla kwalità. Fil-prattika, s’issa, qed jiżviluppa f’diżastru ieħor.  Biċċiet ta’ informazzjoni li qed tasal għandi qed tindika li probabbilment ser jirriżulta li x-xeħħa fil-fondi allokati biex ikun ikkummissjonat l-apparat istallat fl-impjant, hi l-kawża ewlenija tad-diżastru li qed jiżviluppa.

Bħala riżultat ta’ dan kollu irnexxielhom jittrasformaw pass pożittiv f’esperjenza negattiva għal kulħadd. L-impatt ta’ dan kollu ser jibqa’ magħna għal żmien mhux żgħir għax riżultat ta’ dak li ġara qed tissaħħaħ l-isfiduċja fl-awtoritajiet li għal darb’oħra ġie ippruvat li mhumiex kapaċi li jwasslu proġett tajjeb biex jagħti r-riżultat mixtieq.

Għal darb’oħra l-inkonvenjent hu fuq Birżebbuġa, kif ilu jiġri s-snin riżultat ta’ attività industrijali oħra fiż-żona. L-assalt fuq Birżebbuġa tul is-snin ħalla impatt fuq il-kwalità tal-ħajja tar-residenti.  Fuq quddiem nett f’dan ir-rigward hemm it-Terminal tal-Port Ħieles, li hu ta’ inkonvenjent 24 siegħa kull jum. Huwa biss dan l-aħħar li dan l-inkonvenjent beda jiġi indirizzat.

Qiesu dan mhux biżżejjed, fiż-żona industrijali ta’ Ħal-Far, f’data mhux il-bogħod ser ikollna ukoll trakka tal-karozzi li ser tkun iffinanzjata mill-fondi li nġabru mill-bejgħ tal-passaporti! Iktar impatt fuq ir-residenti ta’ Birżebbuġa!

L-aktar attakk riċenti fuq il-kwalità tal-ħajja f’Birżebbuġa qed isir mill-attività ta’ Aquaculture Resources Ltd f’dawn l-aħħar ġimgħat. Dan riżultat tal-irwejjaħ ta’ ħut u drenaġġ ifur fiż-żoni residenzjali.  It-tmexxija tal-kumpanija Aquaculture Resources Ltd kontinwament irrifjutat li terfa’ r-responsabbiltà għall-irwejjaħ tal-ħut u d-drenaġġ ifur għax, qalet, li qed tieħu l-passi kollha meħtieġa fl-impjant tagħha f’Ħal-Far.  

Il-binja li fiha illum hemm l-impjant għall-iproċessar ta’ prodotti tat-tonn kien approvat permezz ta’ applikazzjoni li ma tieħux ħin u dan riżultat ta’ emendi għar-regolamenti tal-ippjanar magħrufa bħala proċeduri tad-DNO (Development Notification Order). Fil-prattika dan elimina l-konsultazzjoni pubblika fil-kaz ta’ xogħolijiet ta’ kostruzzjoni f’żoni industrijali. Riżultat ta’ hekk ħadd ma kien jaf li nhar is-16 ta’ Marzu 2021, l-Awtorità tal-Ippjanar ħarġet il-permess ta’ żvilupp bir-referenza DN01359/20 għall-binja tal-impjant fuq il-Plot 36B fiż-żona Industrijali ta’ Ħal-Far. Il-permess ħareġ f’isem Dr Charlon Gouder, CEO ta’ Aquaculture Resources Limited.

Il-konsultazzjoni pubblika bdiet biss f’Ġunju 2022, ftit wara l-elezzjoni ġenerali. Dan seħħ permezz ta’ dokumentazzjoni dwar il-proċess li jwassal għal permess ambjentali magħruf bħala applikazzjioni IPPC. L-ittri IPPC jfissru Integrated Pollution Prevention and Control u l-proċess hu regolat b’direttiva tal-Unjoni Ewropeja li ġġib dan l-isem u li ilha parti mill-liġi Maltija sa minn meta Malta issieħbet fl-Unjoni fl-2004.

Id-Direttiva IPPC hi intenzjonata biex ikun assigurat li l-impatti ambjentali ta’ numru ta’ proċessi industrijali jkunu indirizzati b’mod integrat. L-impjant tal-prodotti tat-tonn hu soġġett għal din id-Direttiva.

Riżultat ta’ hekk hu meħtieġ il-presentazzjoni ta’ dokumentazzjoni dettaljata teknika li permezz tagħha jkun ċar dwar kif ser issir il-ħidma industrijali, dwar l-impatti ambjentali riżultanti kif ukoll dwar kif inhu ippjanat li dawn ikunu indirizzati.

Din id-dokumentazzjoni ġiet ippreżentata u wara li kienet eżaminata mill-ERA ħareġ il-permess għall-impjant biex jipproċessa l-fdalijiet tat-tonn.

Il-problemi bdew kif beda jopera l-impjant hekk kif beda l-proċess biex l-apparat istallat ikun ikkummissjonat. Jiena infurmat li d-ditta li mingħandha inxtara l-apparat ma ntalbitx biex tieħu ħsieb ukoll li dan ikun ikkummissjonat. Mid-dehra dawk li ġew inkarigati ma tantx kellhom esperjenza f’dan ix-xogħol, kif jidher, wara kollox mir-riżultati miksuba.  

Forsi l-ERA tiftaħ investigazzjoni biex ikun stabilit mhux biss x’ġara imma ukoll min kien responsabbli. Għax hu essenzjali li jkun assigurat li kull min kien involut, inkluż l-ERA, jitgħallem minn din l-esperjenza. Din hi froġa li nħolqot mis-settur privat minkejja li kien qed jaħdem taħt is-superviżjoni tal-ERA! Anke proġett tajjeb irnexxielhom b’inkompetenza kbira jeqirduh!

Ippubblikat fuq Illum: 18 ta’ Diċembru 2022

The art of messing up

The processing plant for Tuna By-Products at Ħal-Far had the potential to be a significant project contributing to the development of the circular economy in Malta. Like many other things it has been messed up.

On paper it was a first-class project. In practice, so far, it is developing into another disaster. Titbits of information which have come my way indicate that eventually it will most probably result that cost-cutting relative to commissioning of the equipment installed in the processing plant is the primary cause of the developing mess.

The end result of this mess-up is that of transforming a potential positive into an absolute negative. The effects of this will be felt for quite some time as it has reinforced the existing mistrust of the authorities who have proven once more that they are incapable of guiding a beneficial project to fruition!

Birżebbuġa is once more shouldering all the resulting inconvenience as it has been doing for many years relative to other industrial operations in the area.  The assault on Birżebbuġa over the years has negatively impacted the quality of life of its residents. The Freeport Terminal tops the list with its round-the-clock inconvenience. It is only relatively recently that this inconvenience has started being addressed.

To add insult to injury the Ħal-Far Industrial Estate will shortly also host a racetrack, the funds for which have already been allocated through the monies collected from the sale of golden passports!  

The latest affront on Birżebbuġa has been the operations of Aquaculture Resources Ltd which commenced earlier this year, and specifically the result of fishy effluent ending up in residential areas in Birżebbuġa.  The management of Aquaculture Resources Ltd has refused to take responsibility for the unbearable fish odours and sewage leaks that have affected the area, stating that the  company has taken measures to contain smells within the tuna by-product processing  plant. 

The building envelope of the tuna byproduct processing plant was approved through a fast-track procedure made possible some years back through amendments to the Development Notification Order. This, in practice, eliminated public consultation for construction works in industrial estates.  As a result, no-one was aware that on 16 March 2021 the Planning Authority issued a development permit bearing reference DN 01359/20 for the Construction of a Tuna Rending Factory on Plot 36B of Ħal-Far Industrial Estate. The permit was issued to Dr Charlon Gouder, the CEO of Aquaculture Resources Limited.

The public consultation only commenced in June 2022, after the general elections, through the publication of the documentation for the environmental permitting process known as the IPPC application. IPPC referring to the Integrated Pollution Prevention and Control as regulated by the EU Directive bearing that name and forming part of Maltese law since EU accession in 2004.

The IPPC Directive seeks to ensure that there is one integrated process addressing the environmental impacts resulting from a number of industrial processes. The tuna byproduct processing plant is subject to this regulatory process.

The IPPC regulatory process requires the presentation of detailed technical documentation relative to the proposed industrial process, the resulting environmental impacts and the manner in which it is proposed to address these same impacts.

This documentation was compiled and after being examined by ERA an operating permit for the Tuna byproduct processing plant was issued.

The problems started with the commencement of operations which were initiated in order to carry out the commissioning of the supplied equipment. I am informed that the suppliers of the equipment were not entrusted to carry out the commissioning. Apparently, those entrusted with the commissioning did not have sufficient experience: the results achieved so far are indicative enough of this fact.

Someday maybe ERA will commission an investigation into what went wrong and who was responsible for the resulting mess.  This is essential in order to ensure that lessons are learnt by all those involved. This is a mess created by the private sector subject to supervision by ERA! They have managed to mess up a good project.

published in The Malta Independent on Sunday : 18 December 2022